- # (Bar size (US))
- The US bar size number, as in #5. For #3 through #8 the number is the nominal diameter in eighths of an inch, so a #5 is 5/8 in (16 mm). Larger sizes (#9 and up) do not follow that rule exactly, so read their diameter from a size table. Read more
- @ (At (spacing))
- Means the bars are spaced at the dimension that follows, as in #5 @ 12" O.C. To count bars, divide the length covered by the spacing and add one. Read more
- ACI (American Concrete Institute)
- The US body that publishes ACI 318, the building code for structural concrete, and many other concrete standards. When general notes say "per ACI 318", cover, laps and hooks follow that code unless the drawings say otherwise.
- ADD'L (Additional)
- Extra bars placed on top of the typical reinforcement in a zone, for example additional top bars over a support. Count them separately from the typical mat.
- Addendum
- A change to the bid documents issued before bids close. Every addendum can change quantities, so confirm you priced the latest one.
- Anchor bolt
- A bolt cast into concrete to attach steel columns, sill plates or equipment. Anchor bolts are usually not rebar scope, but hairpins or ties around them often are. Read more
- ASI (Architect's Supplemental Instruction)
- A US document issued during construction that clarifies or makes a minor change to the drawings. It can change reinforcing, so check whether any ASIs affect the sheets you took off.
- ASTM (ASTM International)
- The standards body whose specifications define materials. ASTM A615 covers the common carbon-steel deformed bars, A706 covers low-alloy weldable bars, and A1064 covers welded wire reinforcement. Read more
- B or BOT (Bottom)
- Bottom layer of reinforcement, as in #5 @ 12 B. In a slab or footing this is the mat nearest the soil or the soffit. Read more
- B.O.F. (Bottom of Footing)
- The elevation of the underside of a footing. Together with the top of footing it gives you the footing depth, which you need for dowel lengths and concrete volume. Read more
- B.O.S. (Bottom of Slab)
- The elevation of the underside of a slab. On steel drawings B.O.S. can also mean bottom of steel, so check the legend. Read more
- Bar list
- A list of every bar to be fabricated: mark, size, number, length, shape and weight. The fabricator cuts and bends from it, and an estimator's takeoff is effectively a priced version of it. Read more
- Bar mark
- A unique label for one bar type on a schedule or placing drawing, such as 5B12 or 01. Every bar with the same mark has the same size, shape and dimensions. Read more
- Bar support
- Any device that holds bars at the correct height and cover during the pour: chairs, bolsters, concrete blocks and spacers. They are usually priced as accessories, separate from the bar weight. Read more
- BBS (Bar Bending Schedule)
- UK, Commonwealth and metric term for the bar list: a table of every bar mark with its size, shape code, dimensions, number and length. In the UK it is usually prepared to BS 8666. Read more
- Beam
- A horizontal member that carries loads across a span by bending. Reinforced with longitudinal top and bottom bars and stirrups. Read more
- Bearing capacity
- The pressure the soil can safely carry under a footing, given by the geotechnical engineer and listed in the general notes. Read more
- Bend diameter
- The diameter of the pin the bar is bent around. Codes set minimum bend diameters by bar size; bending tighter can crack the bar. Read more
- Bending moment
- The internal turning effect in a member caused by loads, which puts one face in tension and the other in compression. The bars are placed on the tension face, which is why reinforcement switches from bottom to top over supports. Read more
- Bid set
- The drawings and specifications issued for pricing. They can change before the construction set, so state in your quote which set and revisions you used.
- Blinding
- UK term for a thin layer of lean concrete placed on the ground under footings to give a clean, level surface. US drawings call it a mud mat.
- Blockout
- A void left in a pour for later work, such as a pipe penetration or a later pour strip. Bars may be cut, trimmed or lapped around it.
- BM (Beam)
- Beam, usually followed by a mark (BM-1, B12) that points to a beam schedule or section with its bars and stirrups. Read more
- Bolster
- A continuous wire bar support, usually for the bottom mat of a slab. Slab bolsters are priced by the linear foot, not by the piece. Read more
- Bottom bars
- Bars in the bottom layer of a slab, beam or footing. In a simply supported or mid-span region they carry the tension from positive bending. Read more
- Boundary element
- The heavily reinforced zone at the ends of a shear wall, with closely spaced ties or hoops around the vertical bars. On a takeoff it behaves more like a column inside the wall. Read more
- Break line
- A zigzag line that shows a drawing has been cut short to save space. The member continues beyond it. Read more
- BS 8666 (British Standard 8666)
- The UK standard for scheduling, dimensioning, bending and cutting of steel reinforcement. It defines the two-digit shape codes used on UK bar bending schedules. Read more
- Caisson
- US term for a large drilled shaft filled with concrete and a cage of reinforcement. Also called a drilled pier. Read more
- Callout
- A note on a drawing that describes reinforcement or points to another view, such as a bar callout (4-#5 T) or a section callout. Read more
- Cantilever
- A member supported at only one end, like a balcony slab. The tension is at the top, so the main bars are top bars anchored back into the supporting structure. Read more
- Chair
- An individual bar support that holds top or bottom bars at the right height. High chairs support the top mat; on UK sites similar supports are also called stools. Read more
- CJ (Construction Joint)
- A planned joint where one pour stops and the next one starts. Bars usually run through it or are lapped across it, so check the detail for dowels or extra bars. Some drawings use CJ for control joint, so check the legend.
- CL or ℄ (Centerline)
- The centerline of a member or a grid. Dimensions taken to centerlines are not clear dimensions, so subtract half widths and cover when you work out bar lengths.
- CLR (Clear)
- A clear dimension, measured between faces with nothing in between. On a rebar callout, 2" CLR is the concrete cover from the bar surface to the concrete face. Read more
- CMU (Concrete Masonry Unit)
- A hollow concrete block. Reinforced CMU walls have vertical bars in grouted cells and often horizontal bars or joint reinforcement, all of which go into the takeoff. Read more
- COL (Column)
- Column, usually with a mark (C1, COL-A) that points to a column schedule listing vertical bars and ties at each level. Read more
- Cold joint
- An unplanned joint formed when fresh concrete is placed against concrete that has already started to set, for example after a delay in the pour. Unlike a construction joint it was not designed.
- Column
- A vertical member that carries loads down from slabs and beams. Reinforced with vertical bars and ties or a spiral. Read more
- Column capital
- A flared enlargement at the top of a column below a flat slab, increasing the support area and punching shear resistance.
- Column schedule
- A table listing each column mark with its size, vertical bars and ties at each level. Read it with the typical column details. Read more
- Combined footing
- One footing that supports two or more columns, used when columns are close together or near a property line. Read more
- Concrete cylinder test
- The US compressive strength test, on 6x12 in or 4x8 in cylinders, usually broken at 7 and 28 days. Many metric markets test cubes instead. Read more
- Construction joint
- A planned stopping point between pours, located as shown on the drawings or approved by the engineer. Reinforcement normally continues through it or is lapped, which can add laps to the takeoff.
- CONT (Continuous)
- The bar runs the full length of the member without a break. If the length is longer than stock length, you must add lap splices to the takeoff. Read more
- Continuous beam
- A beam that runs over more than two supports. It has negative moment over the interior supports, so it needs top bars there. Read more
- Control joint
- A joint sawn, tooled or formed into slabs and walls to make shrinkage cracks happen in a planned line. In slabs on grade it is often called a contraction joint. Read more
- Core
- A group of concrete walls around stairs, elevators or shafts that act together to resist lateral loads. Read more
- Corner bar
- An L-shaped bar placed at wall or beam corners to carry horizontal bars around the corner. Typical details usually require them even when the plan does not show them. Read more
- Coupler
- A mechanical splice that joins two bars end to end, for example with threaded ends or a swaged sleeve. It replaces a lap splice, so take off the coupler count instead of lap length. Read more
- Cover
- The thickness of concrete between the outside of the bar closest to the surface and the concrete face. Bar lengths are member dimension minus cover at each end. Read more
- Crosstie
- A straight bar with a hook at each end that ties across a column, wall or beam to hold bars in position. Usually one end has a 90-degree hook and the other a 135-degree hook. Read more
- CRSI (Concrete Reinforcing Steel Institute)
- The US industry body for reinforcing steel. Its Manual of Standard Practice sets common practice for detailing, bar bend types, fabrication tolerances and bar supports.
- CTRL JT (Control Joint)
- A joint cut or formed in a slab or wall to make shrinkage cracking happen in a straight line. Also written CJ or CTJ, so read the legend before you assume. Read more
- Cube test
- The compressive strength test used in the UK and many metric markets, on 150 mm or 100 mm cubes. Cube strength is higher than cylinder strength for the same concrete, which is why grades like C30/37 give both values. Read more
- Cubic yard
- The US unit for ordering concrete. One cubic yard is 27 cubic feet, or about 0.765 m³. Read more
- Cut length
- The length of straight bar needed to make a bar before bending. For a bent bar it is the sum of its legs with an allowance for bending, which is why detailers and estimators can get slightly different totals. Read more
- Deformed bar
- A reinforcing bar with ribs or lugs rolled on its surface to grip the concrete. Almost all structural rebar is deformed; plain bars are used for some dowels and special items.
- Detail
- An enlarged drawing of a specific condition, such as a corner, a joint or a connection. Typical details apply throughout the job and often contain bars not shown on plans. Read more
- Detail bubble
- A circle with a detail number and the sheet number where the detail is drawn, such as 5/S-501. Read more
- Detailer
- The person who prepares placing drawings and bar lists from the structural drawings. Detailing is more precise than estimating because every bar must be fabricated exactly. Read more
- Development length
- The length a bar must extend beyond the point where it is needed so that it can transfer its full force into the concrete. It depends on bar size, concrete strength, cover and spacing, and is given in the code or the project's lap and development tables. Read more
- DIA or Ø (Diameter)
- Diameter. In metric callouts Ø12 means a 12 mm bar; on US drawings it is used for round items such as piles, columns and sleeves. Read more
- Distribution bar
- UK term for the secondary bars in a one-way slab, running at right angles to the main bars. US drawings often call these temperature and shrinkage bars. Read more
- Dowel
- A short bar cast into one element and projecting to lap or anchor into the next, such as footing dowels for a wall. Count them separately with their own length. Read more
- Drilled pier
- A cast-in-place concrete foundation shaft drilled into the ground, with a rebar cage. Also called a caisson or drilled shaft. Read more
- Drop panel
- A thickened area of a flat slab around a column that increases punching shear resistance and stiffness. It often has its own additional bars.
- DWL (Dowel)
- A dowel bar that connects two separately cast elements, such as a footing to a wall or column. Its length is the embedment on both sides plus any hook. Read more
- E.F. (Each Face)
- The reinforcement shown is placed at both faces of a wall or deep member. A callout of #5 @ 12 EF means two layers, so the bar count doubles. Read more
- E.J. (Expansion Joint)
- A full separation between two parts of a structure that lets them move independently. Bars usually stop at an expansion joint; any dowels across it are detailed to allow movement. Read more
- E.W. (Each Way)
- The bars run in both directions at the spacing shown. #4 @ 12 EW on a slab means one set of bars each way, so take off both directions. Read more
- EA (Each)
- Each. On a callout, 4-#5 EA SIDE means four bars on each side, not four in total.
- Effective depth
- The distance from the compression face of a member to the center of the tension reinforcement. It is why bar position and cover matter to the engineer.
- EL. or ELEV (Elevation)
- Either a height value (EL. 100'-0") or an elevation view of a wall or frame. The context tells you which one.
- Elevation
- A view of a wall, frame or building face looking at it straight on. Wall elevations show openings, steps and bar zones. Read more
- Embed plate
- A steel plate with welded studs or bars cast into the concrete so steel members can be welded to it later. Usually supplied by others, but the rebar around it may need adjusting. Read more
- Epoxy-coated rebar
- Rebar with a fusion-bonded epoxy coating to resist corrosion, usually green or purple. Codes require longer development and lap lengths for coated bars, and it needs coated accessories and tie wire. Read more
- Expansion joint
- A full-depth gap between parts of a structure so they can expand and contract without damage. Bars usually stop on each side. Read more
- f'c (Specified compressive strength of concrete)
- The specified compressive strength of concrete, given in psi (US) or MPa. Unless the notes say otherwise it refers to strength at 28 days, and different elements can have different values. Read more
- F.F. (Far Face)
- The face of a wall farthest from the viewer in the elevation or section being looked at. Used with N.F. (near face) to say which face a bar sits on.
- Flat plate
- A two-way slab of uniform thickness supported directly on columns with no beams, drop panels or capitals. Read more
- Flat slab
- A two-way slab supported directly on columns, usually with drop panels or column capitals. Read more
- Footing schedule
- A table listing each footing mark with its size, depth and reinforcement. Read more
- Formwork
- The temporary molds that hold wet concrete in shape until it can support itself. Called forms in the US and shuttering in the UK. Read more
- Foundation plan
- The plan showing footings, grade beams, piles, pile caps and foundation walls with their marks. Read more
- Framing plan
- A plan of a floor or roof level showing beams, slabs and columns with their marks and slab thicknesses. Read more
- FTG (Footing)
- Footing, usually with a mark (F1, FTG-3) that points to a footing schedule giving size, depth and bars. Read more
- fy (Yield strength of reinforcement)
- The specified yield strength of the reinforcing steel. Grade 60 bars have fy = 60,000 psi (60 ksi); B500B bars have a characteristic yield of 500 MPa. Read more
- GB (Grade Beam)
- A grade beam, a reinforced beam at or below ground level that spans between piles, piers or footings and often supports walls. Read more
- General notes
- The notes at the front of the structural set that list codes, material grades, concrete strengths, cover, laps and standard practices. Read them before starting any takeoff. Read more
- GFRP (Glass Fiber Reinforced Polymer)
- Non-metallic reinforcing bars made of glass fibers in a resin. They do not corrode, but they cannot be bent on site, so bent shapes must be ordered from the supplier. Read more
- Grade 60
- The most common US rebar grade, with a minimum yield strength of 60,000 psi. Grade marks are rolled onto the bar. Read more
- Grade beam
- A reinforced concrete beam at or near ground level that spans between piles, piers or footings and supports walls above. Unlike a strip footing, it is designed to span and not to bear on the soil. Read more
- Grid line
- A reference line on the plan, numbered one way and lettered the other, used to locate columns, walls and dimensions. Read more
- Grout
- A fluid cement-based mix used to fill gaps, such as under column base plates or in the cells of CMU walls. Non-shrink grout is used under base plates and bearing.
- H bar (High-yield bar (UK))
- UK term. Under BS 8666, H16 means a 16 mm high-yield bar of grade B500A, B500B or B500C. A callout like H16-200 B1 gives the size, spacing in mm and layer. Read more
- Hairpin
- A U-shaped bar used to anchor or confine, for example at slab edges, around anchor bolts or at the ends of PT slabs. Read more
- Haunch
- A local deepening of a beam or slab near a support, sloped or stepped. The bars follow the haunch profile, so their lengths change along it.
- Hook
- A bend at the end of a bar that anchors it where there is no room for straight development length. Standard hooks are 90 or 180 degrees for main bars, and stirrups and ties also use 135-degree hooks. Read more
- Hoop
- A closed tie or continuously wound tie with seismic hooks, used for confinement in columns, beams and boundary elements in seismic design. Read more
- I.F. (Inside Face)
- The inside face of a wall, tank or core. Inside and outside faces often have different bar sizes or spacing, so take them off separately.
- IFC (Issued For Construction)
- The drawing set released for building. Estimates are often made from earlier bid or permit sets, so check what changed between your set and the IFC set.
- Isolation joint
- A joint that fully separates a slab from columns, walls or footings so each can move independently. Bars do not cross it. Read more
- Keyway
- A recessed groove formed in a joint so the next pour locks into it and transfers shear. Common at wall-to-footing joints.
- Kicker
- UK term for a short upstand of concrete cast with a slab or base to locate the wall or column formwork above.
- Lap splice
- Two bars overlapped by a set length so force passes from one to the other through the concrete. Each lap adds bar weight, so it must be in the takeoff whenever a run is longer than stock length or there is a construction joint. Read more
- Lateral load
- Horizontal load on a structure, mainly from wind and earthquakes. Shear walls, cores and moment frames resist it. Read more
- Ld (Development length)
- The straight embedment length a bar needs to develop its full strength in tension. Ldh is the equivalent length for a hooked bar. The values come from the governing code and the project's general notes. Read more
- Lintel
- A short beam over a door or window opening that carries the wall above. Common in masonry and concrete walls.
- Load path
- The route a load takes from where it is applied down through slabs, beams, columns and walls to the foundation. Following it helps you understand why bars are where they are.
- Main bars
- The primary reinforcement carrying the main bending tension in a member, for example the short-span bars of a one-way slab. Read more
- Mat
- A layer of bars in two directions, as in top mat and bottom mat of a slab or footing. Each mat is usually two layers of bars.
- Mat foundation
- A single thick reinforced slab under the whole building or a large part of it, supporting all the columns and walls. Called a raft foundation in the UK. It usually has heavy top and bottom mats plus added bars under columns. Read more
- Mesh
- Common UK and AU name for welded wire reinforcement supplied in sheets. UK A-series mesh is square, so A393 has 393 mm² of steel per metre each way. Read more
- MIN (Minimum)
- Minimum. A lap or embedment given as MIN is the shortest length allowed; the bar can be longer, never shorter.
- MPa (Megapascal)
- The metric unit of stress used for concrete and steel strength. 1 MPa is about 145 psi, so 30 MPa concrete is roughly 4,350 psi. Read more
- Mud mat
- A thin layer of lean concrete under footings or mat foundations that gives a clean working surface for placing bars. UK term: blinding.
- N bar (N-class bar (Australia))
- AU term. In Australian notation N12 means a 12 mm deformed bar of 500 MPa normal-ductility steel to AS/NZS 4671. A callout like N16-200 means 16 mm bars at 200 mm centers. Read more
- N.F. (Near Face)
- The face of a wall nearest the viewer in the elevation or section being looked at. The opposite is F.F. (far face).
- N.T.S. (Not To Scale)
- The view is not drawn to scale. Never measure off it; use only the written dimensions. Read more
- Negative moment
- Bending that puts the top of a member in tension, as over the interior supports of continuous beams and slabs and in cantilevers. Needs top bars. Read more
- O.C. (On Center)
- Spacing measured from the center of one bar to the center of the next. #4 @ 12" O.C. means a bar every 12 inches. UK and metric drawings write the same thing as "crs" (centers). Read more
- O.F. (Outside Face)
- The outside face of a wall, tank or core. Compare with I.F. (inside face).
- One-way slab
- A slab that spans mainly in one direction between parallel supports. The main bars run in the short span, with lighter bars the other way. Read more
- Pad footing
- UK term for an isolated footing under a single column. US term: spread footing. Read more
- Pile
- A long foundation element driven or drilled into the ground to carry loads to deeper, stronger soil or rock. Concrete piles have longitudinal bars and ties or spirals. Read more
- Pile cap
- A thick reinforced concrete block that ties the tops of a group of piles together and transfers the column load into them. Read more
- Placing drawing
- US term for a rebar shop drawing: the plans, elevations and bar lists prepared by the detailer that show the ironworkers where each bar mark goes. Read more
- Positive moment
- Bending that puts the bottom of a member in tension, as at mid-span of beams and slabs. Needs bottom bars. Read more
- Precast concrete
- Concrete elements cast in a plant or on site and lifted into place, such as beams, planks and wall panels. Precast rebar is usually the precaster's scope, not the site rebar contractor's. Read more
- psi (Pounds per square inch)
- The US unit for stress. Concrete strength is given in psi, for example 4,000 psi. Read more
- PT (Post-Tensioned)
- Concrete reinforced with high-strength steel tendons that are stressed after the concrete hardens. PT slabs still have ordinary rebar (at columns, edges and openings), which is usually your scope, while tendons are usually a separate supplier's scope. Read more
- Punching shear
- Failure where a column punches through a flat slab or a footing, along a cone-shaped surface around the column. It is resisted by slab thickness, drop panels, or shear reinforcement such as stud rails.
- Raft foundation
- UK and AU term for a mat foundation: a single reinforced slab supporting the whole building. Read more
- Rebar
- Short for reinforcing bar: steel bars cast into concrete to carry tension, because concrete alone is weak in tension. Read more
- Rebar density
- Reinforcement weight per unit volume of concrete, such as kg/m³ or lb/yd³. Useful as a sanity check on a takeoff, not as a replacement for one. Read more
- REINF (Reinforcement or Reinforcing)
- Reinforcement. A note such as "REINF NOT SHOWN FOR CLARITY" means bars exist in that view even though they are not drawn.
- Retaining wall
- A wall that holds back soil. The main vertical bars are on the soil (tension) face and anchor into the footing.
- Revision cloud
- A scalloped outline drawn around the part of a drawing that changed, usually with a triangle (delta) holding the revision number.
- RFI (Request For Information)
- A formal written question from the contractor to the design team about something unclear or conflicting in the drawings. Estimators often list open questions as assumptions or exclusions instead.
- Ribbed slab
- A slab with a thin top and closely spaced ribs underneath, spanning one way. Also called a joist slab or pan joist slab in the US.
- Scale
- The ratio between drawing size and real size, such as 1/4" = 1'-0" or 1:50. Always use written dimensions where they exist, and check the scale bar if a PDF was resized. Read more
- Schedule
- A table on a drawing that lists repeated elements by mark with their sizes and reinforcement, such as beam, column, footing and wall schedules. Read more
- Section
- A view of a member as if it were sliced through, showing its shape, bar positions and cover. Read more
- Section cut
- A symbol on a plan or elevation, with a line and arrows, showing where a section is taken and which way it looks. The label gives the section number and sheet. Read more
- Shape code
- A code that defines a bar's bent shape so the schedule only needs the leg dimensions. BS 8666 uses two-digit codes (00 is a straight bar), while US practice uses the CRSI standard bend types. Read more
- Shear
- Internal force that tends to slide one part of a member past the next. In beams it is resisted mainly by concrete and stirrups. Read more
- Shear stud rail
- A strip with welded headed studs placed around columns in flat slabs to resist punching shear.
- Shear wall
- A concrete or masonry wall designed to resist lateral loads from wind and earthquakes. Read more
- Sheet index
- The list of all sheets in the set, normally on the cover or first sheet. Check it to make sure you have every sheet before you start. Read more
- Shop drawing
- A drawing prepared by a contractor or supplier showing exactly how they will make or install something. For rebar, these are the placing drawings and bar lists. Read more
- SIM. (Similar)
- The condition is similar to the one shown, with minor differences such as dimensions or opposite hand. Treat it as the same reinforcement unless a note says what changes. Read more
- Sleeve
- A pipe or tube cast through concrete so services can pass through later. Bars are moved around small sleeves; large ones may need trim bars.
- Slump
- A measure of fresh concrete workability: the drop in height of a cone of concrete after the mold is lifted, given in inches or mm. Higher slump means a wetter, more fluid mix. Read more
- SOG (Slab On Grade)
- A concrete slab cast directly on the prepared ground. Its reinforcement may be rebar, welded wire reinforcement, fibers, or none. Read more
- SOMD (Slab On Metal Deck)
- A concrete slab cast on a steel deck that acts as formwork and sometimes as reinforcement. Look for welded wire reinforcement or bars over the beams and girders.
- Spacer
- A device that holds bars at the right distance from the formwork to keep cover, often plastic wheels or concrete blocks. In the UK concrete blocks are also called dobies. Read more
- Span
- The distance between supports of a beam or slab. Check whether a given span is center to center of supports or a clear span.
- Specifications
- The written part of the contract documents describing materials, quality and workmanship. Rebar items such as coating, grade and supports may be in the spec rather than on the drawings.
- Spiral
- A continuous helix of bar or wire wrapped around the vertical bars of a round column or pile. Take it off by number of turns or by weight from the pitch and diameter. Read more
- Spread footing
- An isolated footing under a single column that spreads the load over a larger soil area. Usually a square or rectangle with a bottom mat each way. Read more
- Stainless steel rebar
- Corrosion-resistant rebar used in harsh exposures such as marine work and bridge decks. It costs much more than black bar, so it is usually used only in the parts that need it. Read more
- Starter bars
- UK and AU term for dowels that project from a foundation or slab to lap with the bars of the wall or column above.
- Stirrup
- A transverse bar bent around the longitudinal bars of a beam to resist shear. Count them from the spacing zones shown in the beam elevation or schedule. Read more
- Stock length
- The standard length bars are supplied in: 20, 40 or 60 ft in the US, and 6 m or 12 m in metric markets. Runs longer than stock length need laps or couplers. Read more
- Strength class
- The way European and UK standards name concrete strength, such as C30/37: 30 MPa characteristic cylinder strength and 37 MPa characteristic cube strength. Read more
- Strip footing
- A continuous footing under a wall. Also called a continuous or wall footing; it has longitudinal bars and often transverse bars. Read more
- Submittal
- Documents a contractor sends to the design team for review before work, such as shop drawings, mill certificates and mix designs.
- Suspended slab
- UK and AU term for an elevated slab supported on beams, walls or columns rather than on the ground.
- SW (Shear Wall)
- A shear wall, a wall that resists lateral loads from wind or earthquakes. Shear walls often have boundary elements with closely spaced ties at the ends. Read more
- T or TOP (Top)
- Top layer of reinforcement, as in #5 @ 12 T. Over supports of continuous slabs and beams, top bars carry the negative moment. Read more
- T&B (Top and Bottom)
- Bars are placed in both the top and bottom layers. In a slab, #5 @ 12 T&B EW means four layers in total: two directions at the top and two at the bottom. Read more
- T.O.C. (Top of Concrete)
- The elevation of the top surface of concrete. Used where the element is not clearly a slab, wall or footing, such as a pier or pedestal. Read more
- T.O.F. (Top of Footing)
- The elevation of the top of a footing. With B.O.F. it gives the footing depth. Read more
- T.O.S. (Top of Slab or Top of Steel)
- Usually top of slab on concrete drawings and top of steel on steel framing drawings. Check the abbreviation list on the general notes sheet. Read more
- T.O.W. (Top of Wall)
- The elevation of the top of a wall. Wall height for the takeoff is T.O.W. minus the top of the footing or slab it sits on. Read more
- Takeoff
- Measuring quantities from drawings: counting bars, lengths and weights for rebar, or volumes and areas for concrete. The takeoff is the basis of the price. Read more
- Temperature and shrinkage steel
- Minimum reinforcement in slabs and walls to control cracking from shrinkage and temperature change. In a one-way slab it runs perpendicular to the main bars. Read more
- Tendon
- In post-tensioned concrete, the high-strength steel strand inside a sheath that is stressed after the concrete hardens and anchored at the slab edges. Read more
- Tie
- A transverse bar around the vertical bars of a column that holds them in place and confines the concrete. Also used for the tie wire that holds bars together. Read more
- Tie wire
- Soft annealed wire used to tie bars together at intersections. It is a site consumable and is not part of the bar weight. Read more
- Top bars
- Bars in the top layer of a slab or beam. Over supports of continuous members they carry tension from negative bending. Read more
- Transfer beam
- A heavy beam that picks up a column or wall from above and carries it to supports below, where the column grid changes. Usually heavily reinforced.
- Trim bars
- Extra bars placed around openings in slabs and walls to replace the bars cut by the opening. Usually shown in a typical opening detail, not on the plan. Read more
- Two-way slab
- A slab that spans in both directions, supported on all sides or directly on columns. Main bars run both ways. Read more
- TYP (Typical)
- The detail or note applies everywhere the same condition occurs, not only where it is drawn. A typical detail can add bars across the whole job, so find every place it applies. Read more
- Typical detail
- A detail that applies everywhere the same condition occurs, marked TYP. Typical details for corners, openings, intersections and slab edges are a common source of bars missed in takeoffs. Read more
- U-bar
- A bar bent into a U shape, used at wall ends, slab edges and footing edges to close the reinforcement.
- U.N.O. (Unless Noted Otherwise)
- The rule applies everywhere except where the drawings say something different. Also written UNO or U.O.N. (unless otherwise noted). Read more
- Vapor retarder
- A plastic sheet placed under a slab on grade to reduce moisture rising from the ground. Often called a vapor barrier. Read more
- VERT (Vertical)
- Vertical. In walls and columns it marks the vertical bars, which often need dowels or laps at each pour level.
- Wall schedule
- A table listing each wall mark with its thickness and vertical and horizontal bars, often by face. Read more
- Waste factor
- A percentage added to the net takeoff for cutting losses, offcuts and errors. The right figure depends on the job and the supplier, so it should be a deliberate decision, not a habit. Read more
- Waterstop
- A strip of PVC, rubber or swelling material cast across a joint to stop water passing through, common in basements and tanks.
- Weight per foot
- Nominal weight of a bar per unit length, used to convert lengths to weight. For example #4 is 0.668 lb/ft and #5 is 1.043 lb/ft; metric weight is about d²/162 kg/m with d in mm. Read more
- WWF (Welded Wire Fabric)
- Older US name for welded wire reinforcement (WWR). You will still see it on many drawings and specifications. Read more
- WWR (Welded Wire Reinforcement)
- Steel wires welded into a grid and supplied in sheets or rolls. A callout like 6x6-W2.9xW2.9 gives the spacing in inches, then the wire cross-sectional area in hundredths of a square inch. Read more
- Y or T bar (High-yield bar (older UK notation))
- UK term. Older British drawings used T or Y before the diameter for high-yield bars, such as T16 or Y16. Current BS 8666 notation uses H, as in H16. Read more
#
@
A
B
C
D
E
F
G
H
I
K
L
M
N
O
P
R
S
T
U
V
W
Y
No term matches. Try a shorter word.
Free download
The Rebar Callout Cheat Sheet
One printable page: the five questions every callout answers, four labels decoded, and the same bar in six notations. Keep it next to the set of plans.