Structural Drawing Abbreviations: 100+ Common Terms Explained

Structural drawing abbreviations are short codes for positions, elements and instructions, such as EW (each way), EF (each face), T&B (top and bottom), CLR (clear), O.C. (on center) and TYP (typical). Most sets define their own list on the general notes sheet, and that list always wins. The table below covers the abbreviations you will meet on most US-style structural drawings, with notes on the ones that change a bar count.
Read this alongside how to read structural drawings, which explains where these terms appear in a set.
Why structural drawing abbreviations matter for estimating
Most abbreviations are just shorthand for words. A handful are instructions that multiply quantities. "#5 @ 12 EW" is two layers of bars, not one. "#5 @ 12 EF" in a wall is two curtains of bars, one near each face. "TYP" means the same thing happens everywhere similar, even where it is not drawn again. Misread one of these and the whole takeoff for that element is off by a factor of two.
The second reason is consistency. The same letters can mean different things in different offices. CJ is a construction joint on one set and a control joint on another. T.O.S. is top of slab on a concrete job and top of steel on a steel job. When an abbreviation could mean two things, the project's own legend decides.
The full table of structural abbreviations
The meanings below are the common usage on US structural drawings. Check them against the abbreviation list on your general notes sheet.
Position and direction
| Abbreviation | Meaning | Note |
|---|---|---|
| T or TOP | Top (bars in the top layer) | |
| B or BOT | Bottom (bars in the bottom layer) | |
| T&B | Top and bottom | Doubles the bar count: the callout applies to each layer |
| EW | Each way | Bars in both directions of a slab or footing |
| EF | Each face | Bars at both faces of a wall or deep element |
| IF | Inside face | |
| OF | Outside face | |
| NF | Near face | |
| FF | Far face | Also used for finished floor; check context |
| NS | Near side | |
| FS | Far side | |
| HORIZ | Horizontal | |
| VERT | Vertical | |
| LONG | Longitudinal | |
| TRANS | Transverse | |
| ABV | Above | |
| BLW | Below | |
| BTWN | Between | |
| OPP | Opposite | |
| CL or ℄ | Centerline | |
| CTR | Center | |
| CTRD | Centered |
Levels and elevations
| Abbreviation | Meaning | Note |
|---|---|---|
| EL or ELEV | Elevation (a height level, or an elevation view) | Context tells which |
| T.O.C. | Top of concrete | |
| T.O.F. | Top of footing | |
| B.O.F. | Bottom of footing | Sets the depth of excavation and footing |
| T.O.S. | Top of slab, or top of steel | Concrete sets usually mean slab |
| B.O.S. | Bottom of slab, or bottom of steel | |
| T.O.W. | Top of wall | |
| FF or FFE | Finished floor (elevation) | |
| GR | Grade | |
| EOS | Edge of slab | |
| WP | Work point |
Elements
| Abbreviation | Meaning |
|---|---|
| FTG | Footing |
| FDN | Foundation |
| GB | Grade beam |
| PC | Pile cap |
| SOG | Slab on grade |
| COL | Column |
| BM | Beam |
| JST | Joist |
| CANT | Cantilever |
| CMU | Concrete masonry unit |
| CIP | Cast-in-place (concrete) |
| PT | Post-tensioned |
| HSS | Hollow structural section (steel tube) |
| OPNG | Opening |
| CJ | Construction joint, or control joint (check the legend) |
| EJ | Expansion joint |
| JT | Joint |
Reinforcement
| Abbreviation | Meaning | Note |
|---|---|---|
| REINF | Reinforcing, reinforcement | |
| # | Bar size number (#5 = 5/8 in nominal) | See rebar sizes |
| Ø or DIA | Diameter | Metric sets: Ø16 = 16 mm bar |
| db | Nominal bar diameter | Used in lap and hook lengths, such as 48 db |
| CONT | Continuous | Run the bars full length, lapping as needed |
| DWL | Dowel | Short bar tying one pour to the next |
| HK | Hook | |
| STD HK | Standard hook | Dimensions follow the governing code |
| STIRR | Stirrup | |
| TIE | Tie (column or boundary ties) | |
| ADDL | Additional | Extra bars on top of the typical mesh |
| ALT | Alternate | Every other bar, or alternate the direction |
| SPA | Spaces or spacing | 4 SPA @ 12" means four spaces, five bars |
| O.C. | On center | Spacing measured center to center of bars |
| CLR | Clear | Clear cover or clear distance, measured to the bar surface |
| EMBED | Embedment | |
| LAP | Lap splice | |
| WWR | Welded wire reinforcement | |
| WWF | Welded wire fabric | Older term for WWR |
| AB | Anchor bolt | |
| GALV | Galvanized | |
| f'c | Specified compressive strength of concrete | |
| fy | Specified yield strength of reinforcement | Grade 60 = 60 ksi |
Instructions and references
| Abbreviation | Meaning | Note |
|---|---|---|
| TYP | Typical | Applies at all similar locations, drawn or not |
| SIM | Similar | Same idea, but dimensions may differ |
| UNO | Unless noted otherwise | |
| UON | Unless otherwise noted | Same as UNO |
| NTS | Not to scale | |
| EQ | Equal | Equal spaces |
| SYM | Symmetrical | |
| MIN | Minimum | |
| MAX | Maximum | |
| REQD | Required | |
| STD | Standard | |
| EA | Each | |
| W/ | With | |
| W/O | Without | |
| DET or DTL | Detail | |
| SECT | Section | |
| SCHED | Schedule | |
| DWG | Drawing | |
| DIM | Dimension | |
| EXIST or (E) | Existing | |
| (N) | New | |
| VIF | Verify in field | |
| NIC | Not in contract | Do not price it |
| EOR | Engineer of record | |
| ARCH | Architectural (drawings) | |
| MECH | Mechanical (drawings) | |
| STRUCT | Structural |
Units and loads
| Abbreviation | Meaning |
|---|---|
| PSI | Pounds per square inch |
| KSI | Kips per square inch |
| PSF | Pounds per square foot |
| KSF | Kips per square foot |
| PCF | Pounds per cubic foot |
| K or KIP | 1,000 pounds |
| LF | Linear feet |
| SF | Square feet |
| CY | Cubic yards |
| DL | Dead load |
| LL | Live load |
That is over 100 structural drawing abbreviations. For a plain-English definition of the concepts behind them, see the site glossary.
Worked example: decoding a beam note
A beam schedule line reads:
B1, 12" x 24", 3-#6 T&B CONT, #3 STIRR @ 10" O.C., 1 1/2" CLR TYP UNO
Decoded piece by piece:
- 12" x 24": width 12 in, depth 24 in (300 x 600 mm).
- 3-#6 T&B: three #6 (19 mm) bars top and three bottom. Total 6 longitudinal bars.
- CONT: the bars run the full length of the beam, lapped where a bar is not long enough.
- #3 STIRR @ 10" O.C.: #3 (10 mm) stirrups spaced 10 in center to center.
- 1 1/2" CLR TYP UNO: 1.5 in clear cover everywhere, unless a detail says otherwise.
Now the numbers for a beam 24'-0" long between outer faces:
- Longitudinal bar length: 24'-0" minus 1.5" cover at each end = 24.0 - 0.25 = 23.75 ft. That exceeds a 20 ft stock bar, so either 40 ft stock is cut down or the notes' lap rule applies. Assume 40 ft stock, no lap.
- Longitudinal total: 6 x 23.75 = 142.5 ft. At 1.502 lb/ft for #6: 142.5 x 1.502 = 214.0 lb.
- Stirrup count: 23.75 ft = 285 in. 285 / 10 = 28.5, round up to 29 spaces, so 30 stirrups. (Number of bars = spaces + 1.)
The stirrup count comes straight from reading O.C. and SPA correctly. If the note had said "29 SPA @ 10"", you would count 30 stirrups the same way. Run the weights through the rebar weight calculator to check your arithmetic. The callout format itself is covered in depth in how to read rebar callouts.
Abbreviations that trip people up
EW vs EF
EW is about directions, EF is about faces. A footing with "#5 @ 12 EW" has one mat with bars in both directions. A wall with "#5 @ 12 EF" has two curtains. A wall with "#5 @ 12 EW EF" has bars both horizontal and vertical, at both faces: four sets of bars.
TYP and SIM
TYP is a promise that a condition repeats. If a corner detail is marked TYP, it applies to every similar corner in the building, including those that are not cut on any section. SIM says "the same idea, adjust to fit", so check dimensions before you copy a quantity across.
CLR vs O.C.
CLR is measured to the surface of the bar. O.C. is measured between bar centers. Cover rules use clear distance; spacing rules almost always use on center. Our concrete cover guide goes further into cover values.
Metric and UK notation
Outside the US, bar sizes are written in millimetres. On UK and many Commonwealth drawings, H16 means a 16 mm high-yield bar, older drawings use T16 for the same idea, and R10 means a 10 mm plain round bar. Fabric (mesh) is often written with a letter and number such as A393 or B503. See international rebar notation for the full picture.
Frequently asked questions
What does TYP mean on structural drawings?
TYP means typical. The note or detail applies to every similar location in the project, whether or not each location is drawn. Estimators should search the whole set for every place a TYP condition occurs and count it.
What is the difference between EW and EF?
EW (each way) means bars in both horizontal directions of a slab, mat or footing. EF (each face) means bars at both faces of a wall or thick element. EW doubles the directions, EF doubles the layers.
What does UNO mean?
UNO stands for "unless noted otherwise". It sets a default, such as cover or bar spacing, that holds everywhere except where a specific drawing or detail shows something different. UON means the same thing.
What does CONT mean on a rebar callout?
CONT means continuous: the bars run the full length of the element. Where one bar is not long enough, bars are spliced, usually by lapping, following the lap rules in the general notes.
Where can I find the abbreviation list for my project?
It is normally on the first structural sheet, with the general notes and the symbol legend. If an abbreviation on the drawings is not on that list and its meaning affects quantity, ask the engineer of record through an RFI.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.