Structural General Notes: What an Estimator Must Pull Out

Structural general notes are the rules sheet at the front of a structural set. They state the design codes, concrete strengths, rebar grade, cover, lap splice rules and the typical details that apply wherever the drawings are silent. For an estimator, they decide how long every bar is, how much extra steel hides in typical conditions, and what concrete is priced.
Read the structural general notes before you count a single bar. This guide lists what to pull out, section by section, and shows with a worked wall how much they change a takeoff.
Where the general notes live
They are usually on the first one or two structural sheets (S-001, S-002 or S1), together with the abbreviation list, symbol legend and often a set of typical details. On smaller sets they share a sheet with the foundation plan. Some projects also have a written specification. When the notes and the specification disagree, the notes usually say which one governs; if they do not, ask.
The notes are written in sections. Most firms use a similar order: general, design criteria, foundations, concrete, reinforcing steel, masonry, structural steel, and so on. You do not need every section for a rebar and concrete estimate, but you need all of the concrete and reinforcing sections, word for word.
What to pull out of the structural general notes
Here is a checklist of the items that change quantities or prices.
| Section | Item | Why it matters to the estimate |
|---|---|---|
| General | Governing code and edition (for example IBC, ACI 318) | Sets default rules where notes are silent |
| General | "Structural drawings govern" or similar | Who wins in a conflict |
| Foundations | Bearing stratum, footing depth below grade | Excavation and B.O.F. elevations |
| Concrete | f'c by element (for example 3,000 psi footings, 4,000 psi slabs) | Separate concrete line items |
| Concrete | Air entrainment, max water-cement ratio, exposure | Mix price |
| Concrete | Construction and control joint rules | Extra dowels and keys |
| Reinforcing | Bar specification and grade (ASTM A615 Grade 60) | Material price |
| Reinforcing | Weldable bars (ASTM A706) where required | Different material |
| Reinforcing | Coated bars (epoxy ASTM A775, galvanized ASTM A767) | Price and handling |
| Reinforcing | Cover table by element | Bar lengths |
| Reinforcing | Lap splice rule or table | Length of every continuous run |
| Reinforcing | Hook and bend rules | Extra length per bar end |
| Reinforcing | Corner bars, bars at openings, bars at re-entrant corners | Hidden extra bars |
| Reinforcing | Supports and accessories | Chairs and bolsters |
| Reinforcing | Welded wire reinforcement (ASTM A1064) | Mesh line item |
| Reinforcing | Welding of rebar (AWS D1.4) and mechanical splices | Labour and couplers |
| Submittals | Shop drawings and bar lists required | Detailing cost |
Concrete strength
f'c is the specified compressive strength. Notes often give a small table: footings, walls, slabs on grade, elevated slabs, columns. Each strength is a separate concrete item. Units appear as psi in the US and MPa elsewhere; see concrete strength in psi and MPa.
Reinforcing grade
The most common US note is "Reinforcing bars shall conform to ASTM A615, Grade 60". Grade 60 means a minimum yield strength of 60 ksi. Notes may call for ASTM A706 bars where welding is required, or Grade 80 in some elements. Outside the US you will see BS 4449 B500B or IS 1786 Fe500. More detail is in rebar grades.
Cover
The cover table sets the clear distance from the concrete face to the nearest bar. Typical ACI 318 values for cast-in-place, non-prestressed concrete are:
| Condition | Typical cover |
|---|---|
| Cast against and permanently exposed to earth | 3 in (75 mm) |
| Exposed to earth or weather, #6 to #18 bars | 2 in (50 mm) |
| Exposed to earth or weather, #5 and smaller | 1 1/2 in (40 mm) |
| Not exposed, slabs, walls, joists, #11 and smaller | 3/4 in (20 mm) |
| Not exposed, beams and columns (to ties or stirrups) | 1 1/2 in (40 mm) |
These are typical values only. The project's general notes and governing code always win. Concrete cover explains how cover feeds into bar length.
Lap splices
This is the note that moves the most steel. It comes in a few forms:
- A table of lap lengths by bar size and concrete strength.
- A rule in bar diameters, such as "lap 48 bar diameters unless noted otherwise".
- A reference to the code, such as "Class B tension lap splices per ACI 318".
If it is a table, use it as written. If it is a rule in bar diameters, convert: for #5, 48 x 0.625 in = 30 in. The full method is in lap splice length.
Typical details and typical notes
Look for sentences that start with "Provide..." or "At all...". For example: provide corner bars at all wall corners and intersections; provide additional bars around all openings; provide dowels at construction joints matching the wall verticals. None of these bars appear on the plan, yet every one of them is in the contract. The typical details article shows how to count them.
Worked example: a wall with and without the notes
A basement wall is shown on the plan as 60'-0" long and 10'-0" high, with "#5 @ 12" O.C. HORIZ EF". It has two 4'-0" x 4'-0" openings. Suppose the general notes say:
- Cover 2 in clear.
- Lap splices 48 bar diameters unless noted otherwise.
- Provide 2-#5 each face, each side of all openings, extending 2'-0" past the opening corners.
- Bars available in 40 ft lengths.
Horizontal bars, plan only.
- Rows per face: 10'-0" = 120 in. 120 / 12 = 10 spaces, so 11 bars.
- Rows, both faces: 22.
- Length per row: 60'-0" minus 2 in each end = 60 - 0.33 = 59.67 ft.
- Total: 22 x 59.67 = 1,312.7 ft. At 1.043 lb/ft: 1,369.2 lb.
Add the lap note. A 59.67 ft run needs two bars from 40 ft stock, so one lap per row. Lap = 48 x 0.625 = 30 in = 2.5 ft.
- Length per row: 59.67 + 2.5 = 62.17 ft.
- Total: 22 x 62.17 = 1,367.7 ft, or 1,426.5 lb.
Add the opening note. Each opening has four sides, 2 bars per side per face, two faces: 4 x 2 x 2 = 16 bars. Each bar is 4'-0" + 2 x 2'-0" = 8'-0".
- Per opening: 16 x 8 = 128 ft. Two openings: 256 ft.
- Weight: 256 x 1.043 = 267.0 lb.
Result. From the plan alone: 1,369.2 lb. With the general notes: 1,426.5 + 267.0 = 1,693.5 lb. The notes added 324 lb, about 24 percent, to this one wall, and none of it was drawn on the plan. Check the arithmetic with the rebar weight calculator.
A reading routine for general notes
- Read the whole sheet once without a pen. Get a sense of the project and the firm's style.
- Read it again with a highlighter. Mark every number: strengths, covers, laps, extensions, spacings.
- Copy the numbers into your takeoff assumptions sheet. Each element's takeoff should reference the note it used.
- List every "Provide..." note. Each one is a hidden quantity to count later.
- Note the conflicts. If the notes say one thing and a detail says another, write it down and raise an RFI, unless a note explains which governs.
- Re-read on every new issue. Notes get revised too, and a changed lap or cover note changes the entire takeoff.
The order for the rest of the set is in how to read structural drawings, and unfamiliar terms are in the structural drawing abbreviations list.
Frequently asked questions
What are structural general notes?
They are the written rules on the first sheets of a structural drawing set. They cover design codes, loads, materials, cover, lap splices, typical details and inspection requirements, and they apply to the whole project unless a specific drawing says otherwise.
Do general notes override the drawings?
Usually it is the other way around: a specific note or detail on a drawing overrides a general note, which is what "unless noted otherwise" means. But many notes also state which document governs in a conflict, so read that sentence on your project. When in doubt, ask the engineer of record.
Why do general notes matter to a rebar estimator?
Cover changes every bar length, lap rules change every continuous run, and typical notes add bars that are never drawn. An estimate built only from the plans and schedules is almost always short.
What does "lap 48 bar diameters" mean?
It means overlapping bars must extend past each other by 48 times the bar diameter. For a #5 bar (0.625 in) that is 30 in. Whether that value is right for your job is set by the project's own notes and governing code.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.