What Does T&B Mean on Structural Drawings?

T&B means top and bottom. A callout like #5 @ 12" EW T&B tells you that the reinforcement is placed in two mats, one near the top surface and one near the bottom surface of the slab, footing or beam.
Where you see T&B on a drawing
On the drawing you will see T&B on horizontal elements that are thick enough, or loaded enough, to need steel near both surfaces:
- Mat foundations and thick footings:
#6 @ 12" EW T&B - Pile caps:
#8 @ 10" EW T&B - Structural slabs and transfer slabs:
#5 @ 12" EW T&B - Beams and grade beams:
(3) #6 CONT T&B, meaning three continuous bars at the top and three at the bottom
It is the horizontal cousin of EF (each face), which is used mostly on walls. See what EF means.
What T&B changes in a takeoff
T&B doubles the bars for that callout. Combined with EW (each way), it gives four layers of bars: bottom in both directions and top in both directions.
Worked example
A mat footing is 20 ft x 30 ft with #5 @ 12" EW T&B. Ignore cover, laps and hooks here so the logic stays clear.
| Layer | Bars run | Spread over | Number of bars | Length each | Total length |
|---|---|---|---|---|---|
| Bottom, long way | 30 ft | 20 ft | 20 / 1 + 1 = 21 | 30 ft | 630 ft |
| Bottom, short way | 20 ft | 30 ft | 30 / 1 + 1 = 31 | 20 ft | 620 ft |
| Top, long way | 30 ft | 20 ft | 21 | 30 ft | 630 ft |
| Top, short way | 20 ft | 30 ft | 31 | 20 ft | 620 ft |
| Total | 104 bars | 2,500 ft |
At 1.043 lb/ft for #5, that is about 2,608 lb. Read as a single mat, the same footing would come out at 1,250 ft, half the real quantity. In a real takeoff you would also deduct cover from the bar lengths, add laps where bars are longer than stock length (the 30 ft bars are longer than a 20 ft stock bar), and count the chairs or standees that hold the top mat up. Those steps are in how to estimate rebar for a mat foundation.
A common mistake
The usual mistake is counting only one mat, often because the plan view shows the bars once and the "T&B" sits at the end of a long callout. The second mistake is assuming the top and bottom mats are the same when they are not. Many slabs and footings have different steel in each mat, written as two separate callouts:
BOTT: #5 @ 12" EWTOP: #4 @ 16" EW
That is not T&B, and each mat is counted on its own. A slab plan may also show only the extra top bars over supports, with the bottom mat running continuous. Reading a slab reinforcement plan shows how to tell the two apart.
Finally, do not forget the support steel. A top mat does not float: it needs chairs, standees or bolsters, which are usually priced as their own line item.
Frequently asked questions
Is T&B the same as EF?
They mean the same thing in practice (a layer near each surface), but by habit T&B is used for slabs, footings and beams, and EF for walls. Some designers use EF on mats too.
What does EW T&B mean?
Each way, top and bottom: bars in both directions in the top mat and in both directions in the bottom mat. That is four sets of bars.
Is it written T&B or T/B?
Both are used, as are "TOP & BOTT" and "T & B". They all mean top and bottom. The project's abbreviation list on the general notes sheet confirms the meaning.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.