A drilled pier rebar takeoff has two main items per pier: the vertical bars of the cage and the transverse steel around them, which is either a continuous spiral or individual hoops. Count the verticals from the pier schedule and take their length from the cage depth plus any projection above the pier. For a spiral, one turn is the hypotenuse of a right triangle with sides π × D and the pitch, so the length per turn is √((π × D)² + pitch²), multiplied by the number of turns plus the extra end turns.

Closely related names are used for them in different regions and specifications: drilled shafts, caissons, bored piles, CIDH piles. The takeoff method is the same. Read the pier schedule, the pier detail and the general notes together, and the whole cage comes out of a few lines of arithmetic.

Where drilled pier rebar is shown on the drawings

Pier information is usually split over three or four places:

  • Pier plan (often on the foundation plan): pier marks such as P1 and P2 at grid intersections, so you can count them. See reading a pile plan for how these plans are laid out.
  • Pier schedule: diameter, depth or tip elevation, vertical bars, spiral or hoops, for each mark. For example P1 30" DIA 25'-0" 8 #8 VERT #4 SPIRAL @ 6" PITCH.
  • Pier detail: cover to the cage, how far the verticals project above the top of pier, where the spiral starts and stops, extra turns, splice details.
  • General notes: concrete cover, lap lengths, bar grade, and sometimes a note that the pier depth is to be confirmed in the field by the geotechnical engineer.

That last note matters. If the depth can change on site, your takeoff is based on the design depth, and you should say so in your assumptions.

Item Usually found in Typical callout
Pier count and marks Pier or foundation plan P1, P2 at grids
Diameter and depth Pier schedule 30" DIA, 25'-0"
Vertical bars Pier schedule 8 #8 VERT
Spiral Pier schedule or detail #4 SPIRAL @ 6"
Hoops (instead of spiral) Pier schedule or detail #4 HOOPS @ 12"
Projection above pier Pier detail 3'-0" PROJ
Cover General notes or detail 3" CLR

How the cage is built

The cage is assembled flat or upright on site, then lifted into the open shaft. On the drawing you will see:

  • Vertical bars evenly spaced around a circle, running almost the full depth and often projecting up into the grade beam, pile cap or column above.
  • A spiral wrapped around the verticals at a constant pitch, or circular hoops at a spacing, each closed with a lap.
  • Cover measured from the outside of the spiral or hoop to the side of the shaft, and from the bottom of the cage to the bottom of the hole.

Bars that keep the cage centred in the hole (spacers, rollers) and any stiffener rings the cage maker adds for lifting are not always on the design drawings. Take off only what the drawings or the specification show, and list anything else as an exclusion or a question.

25'-0"3'-0" projT/PIER8 #8 vert#4 spiral@ 6" pitch8 #8spiral30" dia
Pier P1 in elevation (left) and plan section (right): eight #8 verticals inside a #4 spiral, projecting 3'-0" above the top of pier into the grade beam (dashed).

Vertical bars

Count: straight from the schedule. "8 #8 VERT" is 8 bars per pier. Multiply by the number of piers of that mark on the plan.

Length: cage length inside the pier plus the projection above it.

Cage length = pier depth − bottom cover (and − top cover if the bars stop inside the pier).

If the verticals are longer than stock length (40 ft or 60 ft are common in the US), add a lap or a coupler at each splice as the detail shows. Deep piers often have splices; shallow building piers often do not. For laps, see lap splice length.

If the verticals finish with hooks into a cap or grade beam, add the hook length from the detail or the hook table. The method is the same as any other bar; rebar cut length formula covers the pieces.

Spiral length: the formula and where it comes from

Unroll one turn of a spiral and it becomes a straight line. Horizontally it travels once round the circle, π × D. Vertically it climbs one pitch. The bar is the hypotenuse:

Length of one turn = √((π × D)² + pitch²)

Use D at the centreline of the spiral bar, not the pier diameter and not the outside of the cage. If the detail gives the cage outside diameter, subtract one bar diameter.

Number of turns = spiral height ÷ pitch, rounded up, plus the extra turns at each end shown on the detail. For column spirals, ACI 318 calls for 1½ extra turns at each end of the spiral for anchorage, and many pier details show the same. The project's detail and governing code decide the number.

one turn of spiral, unrolledpi x D = 73.83 in6 inpitchone turn = 74.07 in
Unrolled, one turn of the P1 spiral is the hypotenuse of a triangle: π × 23.5 in around, 6 in up. The pitch is drawn larger than scale so the triangle is visible.

Notice how little the pitch adds: 73.83 in around, 74.07 in along the bar. For a quick check, π × D × number of turns is close. For the takeoff, use the formula; it costs nothing.

Spirals are often supplied as coils made to the pier's dimensions. A spiral for a long pier may be supplied in pieces and spliced. If the detail shows splices, add a lap (or a mechanical splice) for each one. The example below treats each pier's spiral as one continuous piece.

Drilled pier rebar takeoff: worked example

All values below are this example's. On a real project the schedule, details and general notes govern.

  • P1: 30 in dia, 25'-0" deep, 8 #8 verticals, #4 spiral @ 6" pitch. Quantity: 8.
  • P2: 36 in dia, 30'-0" deep, 10 #8 verticals, #4 spiral @ 6" pitch. Quantity: 4.
  • Cover: 3 in to the outside of the spiral and 3 in at the bottom of the cage.
  • Verticals project 3'-0" above the top of pier into the grade beam, straight. Stock: 40 ft, so no splices.
  • Spiral runs the full cage length, with 1½ extra turns at each end.
  • Weights: #8 = 2.670 lb/ft, #4 = 0.668 lb/ft.

Step 1: cage length

P1: 25'-0" − 3 in = 24.75 ft (297 in).

P2: 30'-0" − 3 in = 29.75 ft (357 in).

Step 2: vertical bars

P1: 24.75 + 3.00 = 27.75 ft per bar. 8 piers × 8 bars = 64 bars × 27.75 = 1,776.0 ft.

P2: 29.75 + 3.00 = 32.75 ft per bar. 4 piers × 10 bars = 40 bars × 32.75 = 1,310.0 ft.

Both are under 40 ft, so no laps.

Step 3: spiral diameter

P1: cage outside diameter = 30 − 2 × 3 = 24 in. Spiral centreline = 24 − 0.5 = 23.5 in.

P2: 36 − 6 = 30 in. Centreline = 29.5 in.

Step 4: length per turn

P1: π × 23.5 = 73.83 in. √(73.83² + 6²) = 74.07 in per turn.

P2: π × 29.5 = 92.68 in. √(92.68² + 6²) = 92.87 in per turn.

Step 5: number of turns

P1: 297 ÷ 6 = 49.5, round up to 50 turns, + 1.5 + 1.5 extra = 53 turns.

P2: 357 ÷ 6 = 59.5, round up to 60, + 3 = 63 turns.

Step 6: spiral length

P1: 53 × 74.07 in = 3,925.8 in = 327.15 ft per pier. 8 piers = 2,617.2 ft.

P2: 63 × 92.87 in = 5,850.9 in = 487.57 ft per pier. 4 piers = 1,950.3 ft.

Step 7: weight

Item Size Total length (ft) lb/ft Weight (lb)
P1 verticals (64 bars) #8 1,776.0 2.670 4,741.9
P2 verticals (40 bars) #8 1,310.0 2.670 3,497.7
P1 spirals (8 piers) #4 2,617.2 0.668 1,748.3
P2 spirals (4 piers) #4 1,950.3 0.668 1,302.8
Net total 11,290.7

Check by size: #8 = 3,086.0 ft × 2.670 = 8,239.6 lb. #4 = 4,567.5 ft × 0.668 = 3,051.1 lb. Sum = 11,290.7 lb.

That is a net weight. Any waste allowance goes on top as a separate, stated line; see rebar waste factor. You can check the unit weights with the rebar weight calculator.

When the pier has hoops instead of a spiral

Some schedules call for individual circular hoops, for example #4 HOOPS @ 12". Each hoop is a circle plus a lap to close it:

Hoop length = π × D (centreline) + lap.

Number of hoops = cage length ÷ spacing, rounded up, + 1.

For P1 with #4 hoops @ 12" and a 20 in closing lap (an example value; the detail gives the real one):

  • Hoop length = 73.83 + 20 = 93.83 in = 7.82 ft.
  • Number = 297 ÷ 12 = 24.75, round up to 25 spaces, + 1 = 26 hoops.
  • Per pier = 26 × 7.82 = 203.3 ft.

Do not compare this number with the spiral above: the spacing is different. The point is the method.

Where drilled pier takeoffs go wrong

  • Using the pier diameter for the spiral. The spiral sits inside the cover. Using 30 in instead of 23.5 in on P1 overstates every turn by about 28%.
  • Forgetting the extra end turns. On P1 they are 3 turns out of 53. Small per pier, but they are on every pier.
  • Missing the projection. The verticals often project above the pier into a cap, grade beam or column. That length may be shown only on the pier detail or the grade beam section.
  • Field depth changes. If the notes say the depth is set in the field, write your design depth in the assumptions so a change can be priced.
  • Counting dowels twice. If the pier verticals are the dowels for the column above, they should not appear again in the column takeoff. See rebar estimate for columns for how column bars start.
  • Belled piers. A bell at the bottom changes the concrete, not necessarily the rebar. Take off bars in the bell only if the detail shows them.

Frequently asked questions

How do you calculate the length of a rebar spiral?

Find the spiral centreline diameter D (cage outside diameter minus one bar diameter). One turn is √((π × D)² + pitch²). Multiply by the number of turns, which is the spiral height divided by the pitch, rounded up, plus the extra turns at each end shown on the detail.

How much rebar is in a drilled pier?

It depends on the diameter, depth and design, so there is no standard figure. In the example here, a 30 in pier 25 ft deep with 8 #8 verticals and a #4 spiral came to about 811 lb (592.7 lb of verticals plus 218.5 lb of spiral). Use a number like that only to check a takeoff.

Is a drilled pier the same as a caisson?

The names overlap and their use varies by region: in many places both mean a hole drilled in the ground, a rebar cage lowered in, and concrete placed. Drilled shaft, bored pile and CIDH pile are closely related names, and some specifications draw distinctions between them. The rebar takeoff method does not change with the name.

Do drilled pier verticals need laps?

Only if they are longer than the stock length or the cage is built in sections. Short building piers often use full-length bars with no splice. Deep piers usually have laps or mechanical splices, and the pier detail shows where.

This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.

Keep reading

The whole library

Free download

The Rebar Callout Cheat Sheet

One printable page: the five questions every callout answers, four labels decoded, and the same bar in six notations. Keep it next to the set of plans.

Plus a few short emails on reading structural drawings. Unsubscribe any time. Privacy.