Vapor Barrier Under Slab: Retarder vs Barrier, 10 vs 15 Mil, and How to Take It Off

8 min read · By a practising structural engineer · Updated November 2026

Plastic sheeting laid under a driveway before concrete
Photo: Gayest Frogs, CC BY-SA 4.0, via Wikimedia Commons

A vapor barrier under slab is a plastic sheet laid on the prepared base before a slab on grade is poured, to slow moisture moving up from the ground into the concrete and the floor finish above it. Most products sold for this job are technically vapor retarders, tested and classed under ASTM E1745, and the drawings usually call for a minimum thickness such as 10 mil or 15 mil. For the takeoff, the plan area is only the start: laps, turn-ups at the edges, and penetrations add to it.

The membrane is a small line item, but it sits under every slab on grade in a building, and it affects the rebar crew directly, because every chair under the slab mat stands on it.

Why a vapor barrier under slab matters

Ground moisture moves up through a slab as vapor. Bare concrete in a warehouse can tolerate that. Floor finishes often cannot: adhesives for vinyl, tile, wood and carpet can fail, coatings can blister, and stored goods can be damaged. The membrane slows that flow.

It also does two practical jobs during construction: it stops the base course from soaking water out of the fresh concrete, and it gives a clean surface to work on. It does not replace waterproofing where there is water pressure from a high water table; that is a different system, detailed separately.

Vapor retarder vs vapor barrier

The two terms are used loosely, sometimes on the same sheet. In practice:

Term What it usually means Where you see it
Vapor retarder A membrane that slows vapor transmission; ASTM E1745 requires a permeance no greater than 0.1 perms ACI documents, ASTM E1745, most specifications
Vapor barrier Common trade name for the same product; some references use it for lower-permeance materials, but the definitions are not consistent Drawings, product names, field language

A perm is a unit of water vapor transmission; lower means less moisture gets through. If the specification names a permeance limit, that number governs over whatever the sheet is called on the drawing.

ASTM E1745 classes

ASTM E1745 is the material specification for plastic vapor retarders used under slabs. It sorts products into Class A, Class B and Class C, with Class A the most durable (highest strength and puncture resistance). All three classes have the same 0.1 perm permeance limit; they differ in strength. The specification for a project typically names the class.

ASTM E1643 is the companion practice for selecting, installing and inspecting the membrane: laps, sealing seams, penetrations and repairs.

Plain construction polyethylene sheet is often not tested to E1745 and may not meet any of its classes. If the specification calls for an E1745 product, generic poly from the yard is not a substitute.

10 mil vs 15 mil

A mil is a thousandth of an inch, so 10 mil is 0.010 in (0.25 mm) and 15 mil is 0.015 in (0.38 mm).

  • 10 mil is the minimum thickness that ACI 302.2R guidance gives for under-slab vapor retarders, and it is common under ordinary slabs.
  • 15 mil products are widely specified where the floor finish is sensitive to moisture or where the sheet takes more abuse during construction: heavy traffic, rebar mats, stone base.

Thickness alone does not decide performance. Two 15 mil sheets can have different permeance and puncture resistance, which is why good specifications name the E1745 class and a permeance limit, not just "15 mil poly".

Where it shows up on the drawings

The membrane rarely gets its own sheet. On the drawing you will see it in four places:

  1. Typical slab on grade section. A dashed or heavy line directly under the slab, labeled "VAPOR RETARDER" or "VAPOR BARRIER", sometimes with the thickness, over "COMPACTED GRANULAR BASE" of a stated depth.
  2. General notes. A note such as "PROVIDE 15 MIL VAPOR RETARDER, ASTM E1745 CLASS A, UNDER ALL INTERIOR SLABS ON GRADE. LAP AND SEAL PER MANUFACTURER." Read it against the general notes for chairs and slab reinforcement.
  3. Edge and thickened slab details. Whether the sheet stops at the slab edge, runs down the thickened edge, or turns up against the foundation wall.
  4. Specifications. Product, class, permeance, lap width, seam tape, penetration boots, and repair method. The architectural specification is often where the full requirement lives.

Some older details show a layer of granular fill placed on top of the membrane, between it and the slab. Guidance on that arrangement has changed over the years, so the section on your drawings decides which way this project goes.

SLAB ON GRADE EDGE (SECTION)6" LAP AT SEAMVAPOR RETARDERCHAIR ON PLATE
The vapor retarder runs under the slab and down the thickened edge. Seams are lapped and taped, and chairs need a base plate so they do not puncture the sheet.

What the rebar crew needs to know

The vapor retarder is usually not in the rebar contract, but it shapes how the rebar is placed:

  • Chairs. Narrow chair legs push through the sheet under load. Slab on grade work uses chairs with sand plates, plastic chairs with wide feet, concrete blocks or continuous bolsters. The chair type changes your accessory takeoff; see rebar chairs and accessories.
  • Dragging bars. Bars and mesh dragged across the sheet tear it. Specifications commonly require damage to be repaired, with patches lapped and taped, before concrete is placed.
  • Dowels and stakes. Anything driven through the membrane becomes a penetration that needs sealing.

A common mistake is to price standard wire chairs for a slab on grade because the general notes were read only for bar sizes. The membrane note is often the reason a different chair is required.

How to take off a vapor barrier under slab

The unit is square feet (or square metres) of material, then converted to rolls using the product's roll size. The steps:

  1. Measure the area to be covered. Slab plan area, plus any extension shown on the edge details (down a thickened edge, up a wall, over a footing).
  2. Lay out the strips. Decide the strip direction, usually along the long side, so there are fewer seams.
  3. Allow for laps. Each seam overlaps; a 6 in (150 mm) lap is commonly specified, but the specification and the manufacturer govern. Each overlap reduces the useful width of a strip.
  4. Round up to whole strips, then to whole rolls.
  5. Add the accessories: seam tape by linear foot of lap, pipe boots or mastic at each penetration, and repair material.

Worked example

This is an invented example. A slab on grade is 50'-0" x 80'-0" (15.2 m x 24.4 m). The edge detail shows the vapor retarder running down the inside face of a thickened edge, which adds about 2'-0" on every side. The specification calls for a 15 mil Class A retarder with 6 in laps, taped. Suppose the product data gives a roll width of 12 ft (check the actual roll size of the specified product).

Step 1: area to cover. Width = 50 + 2 + 2 = 54 ft. Length = 80 + 2 + 2 = 84 ft. Area = 54 x 84 = 4,536 ft². The slab plan area alone is 50 x 80 = 4,000 ft².

Step 2: strips along the 84 ft direction. Useful width of each strip after a 6 in lap = 12 − 0.5 = 11.5 ft. Strips needed = 54 / 11.5 = 4.70, round up to 5 strips. Check: 5 strips cover 12 + 4 x 11.5 = 58 ft, which is more than 54 ft; the extra 4 ft is trimmed.

Step 3: material. 5 strips x 84 ft x 12 ft = 5,040 ft² of sheet. Compared with the slab plan area: 5,040 / 4,000 = 1.26, so 26 percent more material than the slab area suggests.

Step 4: seam tape. 5 strips have 4 seams, each 84 ft long: 4 x 84 = 336 linear ft of lapped seam to tape.

Step 5: penetrations. Count plumbing and conduit penetrations from the plumbing and electrical plans. If there are 12, that is 12 pipe boots or sealed details.

The lesson is in Step 3. Taking the vapor barrier off at plan area ignores edge extensions, laps and trim, and on this slab that would have left out about a fifth of the material.

Common mistakes

  • Using plan area only. Laps, turn-downs and trimming add material, as the example shows.
  • Missing the edge detail. Whether the sheet runs under the thickened edge or stops at it changes the area.
  • Ignoring the class. A note that names ASTM E1745 Class A rules out generic poly.
  • Forgetting accessories. Tape, boots and repair patches are on every specification and in nobody's bid if they are not counted.
  • Wrong chairs. Read the membrane note before you count chairs.

For the slab itself, see slab on grade reinforcement and concrete slab thickness; the concrete calculator handles the volume.

Frequently asked questions

Do you need a vapor barrier under a concrete slab?

Most interior slabs on grade in buildings are detailed with one, and it is normally specified wherever moisture-sensitive floor finishes, adhesives or stored goods are involved. Exterior slabs and some unheated buildings may be detailed without one. The drawings and specifications decide for each project.

Is 10 mil or 15 mil better under a slab?

ACI 302.2R guidance gives 10 mil as the minimum. 15 mil products are often specified where the floor is moisture sensitive or the sheet will take heavy construction traffic. The specification should also name an ASTM E1745 class and a permeance limit, which matter more than thickness alone.

What is the difference between a vapor retarder and a vapor barrier?

Both slow moisture moving up through the slab. ASTM E1745 covers vapor retarders with a permeance of no more than 0.1 perms, and "barrier" is mostly a trade word for the same kind of sheet. Drawings use the words loosely, so follow the permeance and class in the specification.

How much should a vapor barrier overlap?

A 6 in (150 mm) lap with taped seams is commonly specified, but the project specification and the manufacturer's instructions govern. ASTM E1643 covers installation, including seams, penetrations and repairs.

Does the vapor barrier go above or below the gravel?

On many current details the vapor retarder is placed on top of the compacted granular base, directly under the slab. Some details place a layer of fill above it instead. Follow the slab on grade section on the drawings.

This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.

Keep reading

The whole library

Free download

The Rebar Callout Cheat Sheet

One printable page: the five questions every callout answers, four labels decoded, and the same bar in six notations. Keep it next to the set of plans.

Plus a few short emails on reading structural drawings. Unsubscribe any time. Privacy.