The drawing title block is the boxed strip, usually along the right edge or bottom of every sheet, that identifies the project, the firm, the sheet title, the sheet number, the scale, the issue date and the revision history. The sheet number, such as S-101, tells you the discipline and the type of sheet. Reading the title block first is how you make sure you are pricing the current drawing, not an old one.
One of the most expensive takeoff errors is pricing a superseded sheet, and no amount of careful counting fixes it. This guide explains each part of the title block, how sheet numbers are built, and a short routine to confirm your set is current.
Where the drawing title block is and what it contains
On most US sets the title block runs down the right side of the sheet; some offices put it across the bottom. It appears on every sheet in the same position and format, so once you know one, you know them all. Typical contents:
| Field | What it tells you | Why the estimator cares |
|---|---|---|
| Firm name and logo | Who prepared the sheet | Who to send questions to |
| Project name and address | Which job | Avoid mixing two jobs in one folder |
| Project number | The firm's internal job number | Reference on RFIs and correspondence |
| Engineer's seal and signature | The licensed engineer responsible | An unsealed sheet may be a preliminary issue |
| Issue status | e.g. BID SET, ISSUED FOR PERMIT, ISSUED FOR CONSTRUCTION | Tells you what the sheet is good for |
| Issue date | When this version was issued | Compare against the drawing index |
| Revision block | Each revision number, date and description | Shows what changed and when |
| Sheet title | e.g. SECOND FLOOR FRAMING PLAN | Confirms what is on the sheet |
| Scale | Scale of the main views (may say "AS NOTED") | Needed if you ever measure |
| Drawn by / checked by | Initials of the drafter and checker | Minor, but helps in queries |
| Sheet number | e.g. S-201 | The address of the sheet in the set |
Some title blocks also carry a small key plan, a north arrow, a "NOT FOR CONSTRUCTION" stamp or a list of consultants. The fields above are the ones you will use.
How sheet numbers work
Many US firms number sheets following the Uniform Drawing System in the National CAD Standard, or a version of it. A sheet number like S-101 has three parts:
- Discipline letter: S for structural. Others you will see include G (general), C (civil), L (landscape), A (architectural), M (mechanical), E (electrical), P (plumbing) and F (fire protection).
- Sheet type digit: the first number after the letter.
- Sequence number: the last two digits, counting sheets of that type.
The sheet type digits in that system are:
| Digit | Sheet type | Structural example |
|---|---|---|
| 0 | General: notes, symbols, legends | S-001 General notes |
| 1 | Plans | S-101 Foundation plan, S-102 Second floor framing plan |
| 2 | Elevations | S-201 Wall elevations |
| 3 | Sections | S-301 Building sections |
| 4 | Large-scale views | S-401 Enlarged plan at stair core |
| 5 | Details | S-501 Typical concrete details |
| 6 | Schedules and diagrams | S-601 Column and beam schedules |
| 7, 8 | Defined by the user | |
| 9 | 3D views | S-901 Isometric views |
So S-001 is almost always where the structural general notes start, and S-5xx sheets are where typical details live. Not every office follows the system. You will also see S1.1, S-1, S0.01 or a plain running number. The logic of the set is then explained on the drawing index, which is the next thing to read. For what lives on S-001, see general notes on structural drawings.
Sheet numbers are also the addresses used in callouts. A bubble with 3 over S-301 sends you to view 3 on sheet S-301; see sections, details and elevations.
The revision block
Every time a sheet is reissued with changes, a new line goes into the revision block: a revision number or letter, the date, and a short description such as "ADDENDUM 2" or "REVISED PER RFI 14". On the drawing itself, the changed area is circled with a revision cloud and tagged with a triangle (a delta) carrying the same number.
Two habits worth having:
- Read the latest line first. It tells you the current revision and why it was issued.
- Find every delta with that number. The clouds show what changed, but the change can be small, a single bar size or one elevation. On revised sheets some offices keep older clouds, others remove them, so the delta number is your guide.
How revisions, RFIs and addenda flow through a bid is covered in revision clouds, RFIs and addenda.
Issue status: what the sheet is good for
The issue status in the title block tells you the purpose of that version. Common labels are SCHEMATIC DESIGN, DESIGN DEVELOPMENT, 50% CD, BID SET or ISSUED FOR BID, ISSUED FOR PERMIT and ISSUED FOR CONSTRUCTION. A preliminary set can be fine for a budget number, but a bid must be priced on the set the bid documents name. If the sheets are stamped "NOT FOR CONSTRUCTION" or "PRELIMINARY", say so in your quote.
Worked example: checking you have the current set
This is an invented example. The bid documents include Addendum 2, and the drawing index on S-001 lists the structural sheets with their current revisions:
| Sheet | Title | Index says | Your file says |
|---|---|---|---|
| S-001 | General notes | Rev 1 | Rev 1 |
| S-101 | Foundation plan | Rev 2 | Rev 2 |
| S-102 | Second floor framing plan | Rev 2 | Rev 1 |
| S-103 | Roof framing plan | Rev 0 | Rev 0 |
| S-301 | Sections | Rev 1 | Rev 1 |
| S-501 | Typical details | Rev 0 | Rev 0 |
| S-502 | Typical details | Rev 1 | not in folder |
| S-601 | Schedules | Rev 2 | Rev 2 |
Step 1: count the sheets
The index lists 8 structural sheets. Your folder has 7. S-502 is missing, which is easy to miss because the number sequence S-501, S-601 still looks complete.
Step 2: compare revisions sheet by sheet
Six of the eight match. S-502 is missing, and S-102 is at Rev 1 in your folder but Rev 2 on the index, so you are working from a superseded framing plan. Its Rev 2 line would tell you what changed, but you have to get the sheet first.
Step 3: check the index itself
The index is on S-001 at Rev 1. Make sure that S-001 is the latest one too, by checking the addendum cover letter, which lists the sheets it reissues. An old index will confirm an old set.
Step 4: check the scale on the print you are using
S-101 says 1/8" = 1'-0" in the title block. That scale is true only on the full-size sheet. If the set was printed half size (for example 11" × 17" from a 22" × 34" original), every printed inch now stands for twice as much.
Say you measure 1-1/2" on the half-size print. At full size that would be 3". At 1/8" = 1'-0", 3" ÷ 1/8" = 24, so the length is 24'-0". Reading the half-size print at the scale in the title block would give 12'-0", half the real length. Written dimensions are always better than measuring; see how to scale a drawing. A graphic scale bar, if the sheet has one, shrinks with the print and stays correct.
Result: two problems found before a single bar was counted, a missing sheet and an outdated sheet.
A short routine for every new set
- Read the drawing index and count the sheets.
- Check every drawing title block for sheet number, revision and date against the index.
- Read the issue status and note it in your quote.
- Read the latest revision line on each sheet and find its deltas.
- Check whether sheets are full size or reduced before measuring anything.
- Keep superseded sheets in a separate folder marked as such, so nobody picks them up by mistake.
Frequently asked questions
What is a title block on a drawing?
It is the boxed area on every sheet, usually on the right edge or bottom, that gives the project, the firm, the sheet title and number, the scale, the dates, the engineer's seal and the revision history. It identifies the sheet and its version.
What does S-101 mean on construction drawings?
S is the discipline (structural), the 1 is the sheet type (plans in the Uniform Drawing System), and 01 is the sequence number. So S-101 is usually the first structural plan sheet, often the foundation plan. Offices that use other systems explain them on the drawing index.
How do I know if a drawing is the latest revision?
Compare the revision number and date in the title block with the drawing index and with the list of sheets in the latest addendum or bulletin. If any of the three disagree, ask before you price.
What is the revision block?
It is the part of the title block that lists every revision of the sheet, each with a number or letter, a date and a short description. The matching number appears in a triangle next to the clouded change on the drawing.