Revision Clouds, RFIs and Addenda: How Drawing Changes Reach the Estimate

A revision cloud is a scalloped outline drawn around the part of a drawing that changed, with a small triangle (a delta) next to it holding the revision number. The same number appears in the revision block of the title block, with a date and a short description. Addenda, RFI answers and ASIs are the documents that carry those changes during bidding and construction, and every one of them can change a rebar or concrete takeoff.
Drawings are never issued only once. An estimator who prices from an out-of-date sheet, or who misses one cloud, prices the wrong job. This article explains how changes are marked and transmitted, and how to fold them into a takeoff.
What a revision cloud means
A revision cloud draws attention to a change. It does not explain the change: you compare what is inside the cloud with the previous issue to see what is different. Typical changes inside a cloud on a structural sheet:
- A bar size or spacing changed: #5 @ 12" became #5 @ 9".
- A footing or beam size changed.
- An elevation changed.
- A new opening, a new detail reference, or a note added.
Next to the cloud sits the delta, a triangle with a number (or sometimes a letter) inside. The number matches the revision it belongs to.
Practice on old clouds varies. Many offices clear the clouds from earlier revisions so that only the current changes are clouded, and the deltas stay as a record. Others leave all clouds in place. Either way, the revision block tells you the history.
The revision block
Every sheet's title block has a revision block (or revision table): one line per issue, with the revision number or letter, the date, a short description ("Issued for bid", "Addendum 2", "Issued for construction") and often the initials of who issued it.
Two habits help:
- Check the latest revision on every sheet, not just the cover sheet. Sheets are reissued individually, so S-201 may be on revision 3 while S-101 is still on revision 1.
- Check the drawing list. Most sets include a sheet index on the cover or first general sheet, often with the current revision of each sheet. Compare it with what you have.
Addenda: changes during bidding
An addendum (plural addenda) is a document issued to all bidders during the bidding period, before bids are due. It modifies the bidding documents: revised sheets, revised specifications, answers to bidders' questions, sometimes a changed bid date.
What this means for the estimator:
- Addenda are part of the bid. Bid forms commonly ask the bidder to acknowledge each addendum received.
- An addendum can arrive days before the bid date and change quantities. A late addendum with clouded reinforcement changes means a re-check of the takeoff, not a note in the margin.
- Read the addendum text itself, not just the attached sheets. A one-line text change ("all slab top bars to be epoxy coated") can change the whole price without any drawing being clouded.
RFIs: questions and answers
An RFI (request for information) is a formal written question from the contractor (or during bidding, a bidder) to the design team, asking them to clarify a conflict, an omission or something unclear: a bar callout that does not match the section, a missing dimension, two details that disagree.
During bidding, questions are usually routed through the bidding process and answered to all bidders by addendum. During construction, an RFI gets a written response, which may include a sketch (often marked SK-1, SK-2) or a revised detail.
An RFI response that adds or changes reinforcement is a change to the work. Whether it is priced as a change depends on the contract, but the takeoff has to be updated either way.
ASIs and bulletins
During construction, design changes are often issued through documents such as:
- ASI (Architect's Supplemental Instructions), a standard form used to issue clarifications or minor changes.
- Bulletins or revision packages, which reissue a group of revised sheets with clouds and deltas, often with a narrative describing each change.
- Change orders and similar documents, which formally change the contract scope, price or time.
The names vary by country and contract form. What matters for the estimator is the same: each issued change is checked against the takeoff and the difference is priced or recorded.
| Document | When | Who issues it | Effect on the takeoff |
|---|---|---|---|
| Revision cloud and delta | Any reissue | Designer | Points to what changed on the sheet |
| Addendum | Bidding period | Owner or design team, to all bidders | Changes what you bid |
| RFI response | Bidding or construction | Design team, in answer to a question | May add or change bars |
| ASI or bulletin | Construction | Architect or design team | Revised work, often priced as a change |
| Change order | Construction | Owner and contractor, signed | Formal change to scope, price or time |
Worked example: pricing a revision
This is an invented example. You have taken off a floor from the bid set. Addendum 2 arrives with sheet S-201 at revision 2, and two clouds.
Cloud 1: top bars over six column lines changed from #5 @ 12" to #5 @ 9". Each set is 12'-0" long and ranges over 20'-0".
- Original count per location: 240 ÷ 12 + 1 = 21 bars.
- Revised count per location: 240 ÷ 9 = 26.7, round up to 27 spaces, + 1 = 28 bars.
- Difference: 7 bars × 12.0 ft = 84.0 ft per location.
- Six locations: 504.0 ft × 1.043 lb/ft = +525.7 lb of #5.
Cloud 2: footing F2 (four on the plan) changed from 8'-0" square with 9 #6 EW to 9'-0" square with 10 #6 EW. Cover 3 in.
- Original: 18 bars × (96 − 6) in = 18 × 7.5 ft = 135.0 ft per footing.
- Revised: 20 bars × (108 − 6) in = 20 × 8.5 ft = 170.0 ft per footing.
- Difference: 35.0 ft per footing × 4 = 140.0 ft × 1.502 lb/ft = +210.3 lb of #6.
The footing change also changes the concrete: each F2 was 8 × 8 × 2 = 128 ft³ and is now 9 × 9 × 2 = 162 ft³ if the depth stayed at 2'-0". That is 34 ft³ more per footing, 136 ft³ for four, about 5.0 yd³. The concrete calculator does this conversion.
Record both changes against the revision number in your takeoff, so anyone checking can see which quantities came from which issue. Bar weights are the standard ASTM A615 values (#5 = 1.043 lb/ft, #6 = 1.502 lb/ft).
A routine for tracking changes
- Keep a drawing register: every sheet, its current revision and date, and the addenda received.
- When a new issue arrives, compare revision numbers sheet by sheet before you open anything else.
- Go through every cloud, and also read the addendum text for unclouded changes.
- Update the takeoff line by line, tagged with the revision or addendum number.
- Re-check totals: a changed footing size also changes dowels, concrete, excavation and formwork.
- Raise an RFI or bidder question for anything still unclear, rather than guessing.
Missing a revision is one of the classic rebar takeoff mistakes. A clean method for the takeoff itself is in how to do a rebar takeoff. Once the job is awarded, changes also flow into the detailer's placing drawings; see shop drawings vs design drawings.
Frequently asked questions
What does a triangle with a number mean on a drawing?
It is a revision delta. The number is the revision in which that change was made, and it matches a line in the sheet's revision block. It usually sits next to a revision cloud around the changed area.
What is the difference between an addendum and a revision?
A revision is any reissue of a drawing, marked in its revision block. An addendum is a bidding-period document sent to all bidders that may include revised sheets, specification changes and answers to questions. Revised sheets issued in an addendum carry their own revision numbers.
What is an RFI in construction?
An RFI, or request for information, is a formal written question to the design team about something unclear, missing or conflicting in the documents. The answer is written and may include a sketch or revised detail. If the answer changes the work, the takeoff must be updated.
Do I need to re-check my takeoff after every addendum?
Yes, for any addendum that touches the work you are pricing. Read both the revised sheets and the addendum text, since some changes are written only in the text. Tag each change in the takeoff with the addendum number.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.