Shop Drawings vs Design Drawings: Who Draws What, and What You Bid From

Design drawings are produced by the structural engineer of record and show what the structure must be: sizes, bar sizes, spacing, laps and details. Shop drawings for rebar, usually called placing drawings, are produced by a detailer working for the fabricator or contractor and show how the structure will be built: every bar with a mark, quantity, length and shape, plus a bar list for the shop. The estimator bids from the design drawings, because the shop drawings do not exist yet at bid time.
The two sets describe the same steel in different languages. Knowing which one you are holding, and what it is for, avoids a whole class of mistakes.
Design drawings: what the engineer issues
Design drawings (also called contract drawings or structural drawings) are part of the contract documents, together with the specifications. They are sealed by the engineer of record and they show:
- Member sizes and locations, with grids and elevations.
- Reinforcement by callout and schedule: "#5 @ 12" EF", "4 #9", "9 #6 EW".
- Typical details for laps, hooks, corners, openings and dowels.
- General notes: materials, grades, cover, lap tables. See general notes on structural drawings.
What they usually do not show: individual bar lengths, where each lap falls along a long run, the cut length of each bent bar, or how many separate pieces make up one line of reinforcement. Those decisions are left to the detailer, within the rules the engineer sets.
Shop drawings: placing drawings and bar lists
For reinforcing steel, the shop drawings normally have two parts.
Placing drawings (also called rebar shop drawings or detailing drawings) show the ironworkers where every bar goes. Each bar or group of bars carries a bar mark that ties it to the bar list. Placing drawings show laps at actual positions, bar supports and chairs, and the sequence of pours where it matters.
Bar lists (bending schedules or cutting lists) tell the fabrication shop what to cut and bend: bar mark, size, quantity, total length, shape code and bending dimensions. Outside the US this is usually called a bar bending schedule, with shapes from a standard code; see also rebar shape codes.
In US practice, rebar detailing generally follows the ACI Detailing Manual and the CRSI Manual of Standard Practice, together with the project's own specification.
| Design drawings | Rebar shop drawings | |
|---|---|---|
| Produced by | Structural engineer of record | Rebar detailer (for fabricator or contractor) |
| Purpose | Define the design | Fabricate and place the bars |
| Part of the contract? | Yes, contract documents | No, a submittal |
| How bars are shown | Callouts, schedules, typical details | Every bar with a mark, quantity, length, shape |
| Laps | Lap rules and lap table | Actual lap positions |
| Issued when | Before bidding | After award, before fabrication |
| Used for | Bidding, design intent, review | Shop fabrication and field placing |
The submittal and review process
Shop drawings are a submittal: the contractor sends them for review before fabrication. A typical route:
- The detailer prepares placing drawings and bar lists from the latest design drawings.
- The contractor (or the fabricator for the contractor) checks and submits them.
- The engineer of record reviews them for general conformance with the design.
- They come back with a review stamp.
Review stamp wording varies by office, but it typically has a few boxes along these lines:
- No exceptions taken (or "Reviewed"): proceed.
- Make corrections noted (or "Reviewed as noted"): proceed, incorporating the marked corrections.
- Revise and resubmit: correct and send again before fabrication.
- Rejected: does not meet the design.
Stamps usually carry text saying the review is for general conformance with the design concept and does not relieve the contractor of responsibility for dimensions, quantities and coordination. Read the actual stamp and the project specification for the exact terms.
A practical point: a shop drawing marked "make corrections noted" is not a design change. If the reviewer's notes add reinforcement beyond the design drawings, that question goes back through the contract process, the same way as an RFI or revision.
What the estimator bids from
At bid time, the estimator has the design drawings, the specifications and any addenda. Placing drawings are produced after award. So the estimate has to do what the detailer will later do in full, but at the level of detail needed for a price:
- Count bars from spacing and ranges.
- Add laps on long runs, using the project's lap table and the stock lengths available (commonly 20, 40 or 60 ft in the US, 6 or 12 m in metric markets).
- Add hooks, bends, dowels and the bars hidden in typical details; see typical details and hidden rebar.
- Allow for waste and accessories.
On a project already under way, an estimator pricing a change may also see placing drawings. They are useful to check quantities, but the contract quantity is defined by the design drawings and the issued changes, not by the detailer's interpretation. The difference between the two roles is covered in rebar detailing vs estimating.
Worked example: one wall, two presentations
This is an invented example. A wall is 80'-0" long and 10'-0" high. The design drawing says "#5 @ 12" EF HORIZ, lap per schedule", and the project's lap schedule gives 2'-6" for #5 horizontal bars in this wall. Cover at the wall ends is 3 in.
How the estimator takes it off
Rows per face = 120 in ÷ 12 + 1 = 11. Two faces (EF = each face) = 22 rows.
Run length per row = 80'-0" − 3 in − 3 in = 79'-6" = 79.5 ft.
With bars no longer than 60 ft available, each row needs one lap. Length per row = 79.5 + 2.5 = 82.0 ft.
Total = 22 × 82.0 = 1,804.0 ft. Weight = 1,804.0 × 1.043 lb/ft = 1,881.6 lb of #5.
How the detailer shows it
The detailer decides where the lap goes and how to split the row. One option: a 40'-0" bar (5W1) plus a second bar of 79.5 − 40.0 + 2.5 = 42'-0" (5W2). In this example's marking system the first digit of the mark is the bar size; mark systems vary by detailer.
Bar list:
| Mark | Size | Qty | Length | Total ft | Weight (lb) |
|---|---|---|---|---|---|
| 5W1 | #5 | 22 | 40'-0" | 880.0 | 917.8 |
| 5W2 | #5 | 22 | 42'-0" | 924.0 | 963.7 |
| Total | 44 | 1,804.0 | 1,881.6 |
The weight is the same, because the estimator already allowed for the lap. Where estimates and bar lists differ in practice, it is usually in the things the design drawing shows only by typical detail: corner bars, bars at openings, extra laps from pour breaks, and the staggering of laps. Bar weights here are the standard ASTM A615 value for #5 (1.043 lb/ft).
Common mistakes
- Bidding from an old set. Shop drawings are produced from the latest revision; your estimate must be too.
- Treating the shop drawing as the design. If the placing drawing and the design drawing disagree, the design drawing and issued changes govern unless the engineer says otherwise.
- Forgetting construction joints. The detailer adds laps where the contractor plans pour breaks. The estimate should anticipate them; see construction joints and rebar.
- Mixing up "reviewed" and "approved". Stamp wording differs, and "reviewed" may not mean the same as "approved". Read what the stamp actually says.
Frequently asked questions
Who prepares rebar shop drawings?
Usually a rebar detailer, working for the reinforcing steel fabricator or for the contractor. The detailer works from the engineer's design drawings and specifications. The engineer of record then reviews the submittal.
Are shop drawings part of the contract documents?
Generally no. They are submittals that show how the contractor intends to meet the contract documents. The design drawings and specifications are the contract documents, but always check the project's own contract terms.
What is a bar list?
A bar list is the table the fabrication shop uses to cut and bend the bars. For each bar mark it gives the size, quantity, length, shape and bending dimensions. It goes together with the placing drawings that show where each mark is placed.
Can I estimate rebar from shop drawings?
Only once they exist, which is after award. Bids are prepared from the design drawings. Later, placing drawings and bar lists are useful for checking quantities and pricing changes.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.