Embed Plates and Anchor Bolts on Drawings: Schedules, Scope and Rebar Congestion

7 min read · By a practising structural engineer · Updated November 2026

3D view of a steel column on a base plate over a concrete footing
3D illustration: The Bending Moment

Embed plates are steel plates cast into the face of concrete, with headed studs or welded bars anchoring them, so that steel members, railings or equipment can be welded or bolted to the concrete later. Anchor bolts (anchor rods) are cast into footings, piers and walls to hold down steel columns and other items. On drawings both are shown with tags that point to an embed schedule or a base plate detail, and although they are usually not part of the rebar quantity, they decide where the bars can go.

For a rebar or concrete estimator, embeds are a strange item: you rarely price the steel in them, but you have to find every one, because they bring extra bars, change bar positions and can stop a pour if they are missed. This guide shows how they appear on the drawings and works through a small embed schedule.

How embed plates are shown

On plans and elevations

An embed plate is drawn as a small rectangle on the face of a wall, beam, slab edge or column, with a tag such as E1, EP1 or EMB-1. On plans it appears at slab edges and wall faces; on wall elevations it appears as a rectangle at its height, often with a dimension to the top of the plate or the centre line. Some sets show embeds only on the steel or architectural drawings, with a note on the concrete sheets such as "SEE STEEL DRAWINGS FOR EMBEDDED ITEMS". That note is the only warning you get.

The embed schedule

The tag is a key to an embed schedule or an embed detail sheet. A typical schedule:

Mark Plate Anchors Finish Remarks
E1 PL 1/2" × 8" × 12" 4 - 3/4" dia × 6" headed studs Galvanized Wall face, see elevations
E2 PL 3/4" × 10" × 16" 6 - 3/4" dia × 6" headed studs Galvanized Beam end, add 2 #4 hairpins per detail 7/S-502

Plate size is written thickness × width × length. Anchors are usually headed shear studs or deformed bar anchors (DBA), welded to the back of the plate. The remarks column is where the rebar hides: added hairpins, U-bars or trim bars that the embed needs.

How anchor bolts are shown

Anchor bolts appear in three places:

  • The anchor bolt plan or column base plan, which locates each group of bolts from the grid, often as a separate steel sheet.
  • The base plate detail, which gives the bolt diameter, number of bolts, embedment depth, projection above the concrete, the bolt type (headed, hooked, threaded with a nut and plate washer at the bottom), the grout thickness and the base plate.
  • The general notes or specification, which give the material, commonly ASTM F1554 Grade 36, 55 or 105 in US practice.

A typical callout reads "4 - 3/4" DIA ANCHOR RODS, ASTM F1554 GR 36, 1'-6" EMBED". The projection above the concrete is shown on the detail, set so the nuts and washers fit over the base plate and grout.

For the steel side of these drawings, see how to read structural steel drawings.

E1PL 1/2x8x124 STUDSBARS EFSTUD vsBAREMBED IN WALL4-AB 3/4"EMBED1'-6"BASE PLGROUTPIERANCHOR BOLTS
Left: the studs of embed E1 reach past the wall's vertical bars, so bar and stud positions must be coordinated. Right: anchor bolts cast into a pier sit inside the pier bars and ties. Not to scale.

Who supplies them

Embeds and anchor bolts are steel items, not reinforcing bars. On many US jobs they are furnished by the structural steel fabricator or the miscellaneous metals supplier and set in the forms by the concrete contractor, but this varies. The specification sections (concrete under Division 03 and metals under Division 05 in the usual MasterFormat layout) and the contract scope decide who furnishes, who sets, and who surveys the positions. Read the scope before you include or exclude them, and state your assumption in your quote.

Why embed plates are not in the rebar quantity

  • They are not reinforcing steel. The plate, studs and bolts are fabricated steel items priced by weight or by piece under metals.
  • They are often designed and detailed by the steel side, so their quantities come from the steel drawings.
  • A rebar takeoff that includes them double counts with the steel supplier.

What does belong in the rebar quantity is any bar that the embed detail adds: hairpins, U-bars, extra ties around anchor bolts in a pier, trim bars around a large plate. These are drawn in the embed detail or written in the schedule's remarks, and they are easy to miss. More on this kind of hidden steel in typical details and hidden rebar.

Why they cause congestion

A plate with studs or an anchor bolt group takes up space inside the cage. Common problems:

  • Studs clash with bars. A 6" stud behind a plate reaches through the outer layer of bars and sometimes the inner one. Bars may have to be shifted or the stud layout changed.
  • Embeds at beam ends. The end of a beam already holds the top bars, stirrups and column bars. A plate with anchors there is often where the cage cannot close.
  • Anchor bolts in piers. The bolts sit inside the ties and vertical bars of the pier and must line up with the holes in the base plate, so the bolt template, the pier bars and the ties must be set together.
  • Fixed positions. An embed has to be exactly where the steel or equipment will connect to it. When a bar is in the way, it is usually the bar that moves, not the plate.

These problems are solved on shop drawings and with RFIs, but the estimator should flag heavily embedded areas, because they slow placing. See rebar congestion and constructability.

Worked example: reading an embed schedule

This is an invented example. Using the schedule above, the plans and elevations show:

  • 18 × E1 on wall faces.
  • 6 × E2 at beam ends.
  • 12 steel columns, each on a pier with 4 - 3/4" anchor rods, 1'-6" embedment.
  • Detail 7/S-502: each E2 gets 2 #4 hairpins, each 4'-0" developed length.

Step 1: count the items

E1 = 18, E2 = 6, anchor rods = 12 × 4 = 48. Headed studs: 18 × 4 + 6 × 6 = 72 + 36 = 108.

Step 2: plate weights (for the steel supplier, not the rebar quantity)

Steel weighs 490 lb/ft³, which is 0.2836 lb/in³, or about 40.8 lb per square foot per inch of thickness.

  • E1: 8 × 12 × 0.5 = 48 in³ × 0.2836 = 13.6 lb per plate. 18 plates = 245.0 lb.
  • E2: 10 × 16 × 0.75 = 120 in³ × 0.2836 = 34.0 lb per plate. 6 plates = 204.2 lb.

Plates total 449.2 lb, before studs. This number goes to whoever furnishes embeds. It does not go in your rebar total.

Step 3: the rebar the embeds add

E2 hairpins: 6 embeds × 2 = 12 hairpins × 4.0 ft = 48 ft of #4. At 0.668 lb/ft: 48 × 0.668 = 32.1 lb.

This 32.1 lb does go in the rebar quantity, under the beam or wall it belongs to. Check it with the rebar weight calculator.

Step 4: what to note in the estimate

Item Quantity In rebar quantity?
E1 plates 18 (245.0 lb) No: by metals supplier
E2 plates 6 (204.2 lb) No: by metals supplier
Headed studs 108 No: part of the embeds
Anchor rods 3/4" 48 No: by steel supplier
Hairpins at E2 12 #4 × 4'-0" (32.1 lb) Yes
Setting embeds and rods 24 embeds, 12 rod groups Depends on contract scope

The tonnage of added rebar is small. The value of the exercise is that you found every embed, know which pours they sit in, and can tell the placing crew where to expect trouble.

Common mistakes

  • Missing the note that embeds are on another discipline's drawings.
  • Pricing embed steel as rebar, or leaving out the added hairpins because "embeds are by others".
  • Not checking scope for setting. Furnishing and setting are often by different trades.
  • Ignoring congestion at beam ends and pier tops when pricing labour.

Frequently asked questions

What is an embed plate in concrete?

An embed plate is a steel plate cast flush with a concrete surface, anchored by headed studs or welded deformed bars on its back. Later, steel members, brackets, railings or equipment are welded or bolted to it.

Are anchor bolts part of the rebar package?

Usually not. Anchor bolts are steel items, typically supplied with the structural steel and set by the concrete contractor, though the contract decides. Any extra bars around the bolts, such as ties in the top of a pier, are rebar and are counted with the pier.

What is an embed schedule?

It is a table on the drawings that lists each embed mark with its plate size, number and type of anchors, finish and notes. The plans and elevations show where each mark goes, and the schedule says what it is.

What does ASTM F1554 mean on an anchor bolt callout?

ASTM F1554 is the US standard specification commonly used for anchor rods cast into concrete. It has grades 36, 55 and 105, which refer to the minimum yield strength in ksi. The callout or general notes give the grade for your project.

This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.

Keep reading

The whole library

Free download

The Rebar Callout Cheat Sheet

One printable page: the five questions every callout answers, four labels decoded, and the same bar in six notations. Keep it next to the set of plans.

Plus a few short emails on reading structural drawings. Unsubscribe any time. Privacy.