To read structural steel drawings, you need three things: the shape names (W12x26, HSS6x6x1/4, L4x4x3/8), the framing plan notation that puts those shapes on grid lines with marks, camber and top-of-steel elevations, and the details that connect steel to concrete. The shape name tells you the profile and size, the plan tells you where it goes and at what height, and the details tell you what gets cast into the concrete.

This guide explains how to read structural steel drawings from the point of view of someone who prices or builds the concrete: what the notation means, and what you must take from the steel sheets even when steel is not your trade.

Steel shape designations (AISC naming)

US steel shapes are named the way the AISC Steel Construction Manual lists them. The pattern is: letter for the shape family, then a size, then a weight or thickness.

Designation Family What the numbers mean
W12x26 Wide flange Nominal depth 12 in, weight 26 lb/ft
HSS6x6x1/4 Square or rectangular hollow section Outside 6 in x 6 in, nominal wall 1/4 in
HSS6.625x0.280 Round hollow section Outside diameter 6.625 in, nominal wall 0.280 in
C10x15.3 American standard channel Depth 10 in, weight 15.3 lb/ft
MC12x31 Miscellaneous channel Depth 12 in, weight 31 lb/ft
L4x4x3/8 Equal leg angle Legs 4 in and 4 in, thickness 3/8 in
L6x4x1/2 Unequal leg angle Legs 6 in and 4 in, thickness 1/2 in
WT6x13 Tee cut from a W Depth about 6 in, weight 13 lb/ft (half of a W12x26)
HP12x53 Bearing pile Depth 12 in, weight 53 lb/ft

W shapes

The first number of a W shape is the nominal depth. The real depth varies by weight within a group: a W12x26 is about 12.2 in deep, and heavier W12s are deeper. If you need the exact depth (for example to set a pocket in a concrete wall), take it from the AISC shape tables or from the steel shop drawings, never from the name.

The second number is weight per foot. That makes steel tonnage simple: a W12x26 that is 30 ft long weighs 30 x 26 = 780 lb.

HSS

Hollow structural sections are named by outside dimensions and wall thickness. HSS8x4x3/8 is 8 in by 4 in outside with a 3/8 in nominal wall. The first dimension is usually the larger one. Round HSS are named by outside diameter and wall.

Angles and channels

For angles, the legs come first and the thickness last: L4x4x3/8. For an unequal angle, the plan or detail must tell you which leg is vertical, often with a note like "LLV" (long leg vertical). Channels follow the W pattern: depth, then weight.

Outside the US

UK and many Commonwealth sets use BS EN names such as 305x165x40 UB (universal beam: serial size 305 x 165 mm, 40 kg/m). European sets use IPE and HEA/HEB series. The logic is the same: the name gives size and either weight or a series number. For bar notation in other countries, see international rebar notation.

Reading a steel framing plan

A steel framing plan looks down on one level and draws each member as a single line between grid lines.

1 2 A B W18x35 W18x35 W12x26 c=3/4" (18) W12x26 W12x26 T.O.S. EL. 112'-0" U.N.O.
One bay of a framing plan. Each line is a member; the text along it gives its size, camber (c=3/4") and, in brackets, the number of shear studs. A plan note gives the top-of-steel elevation unless noted otherwise.

Beam and column marks

Each line carries its shape size. Columns are marked at grid intersections, usually with a filled square or an I symbol, and their sizes come from a column schedule rather than the plan. Some sets give pieces an erection mark (B1, G3, C2) and list sizes in a schedule. Beams spanning between columns on grid lines are often called girders; beams framing into girders are just beams or filler beams.

Camber

A note like "c=3/4"" on a beam means the fabricator bends it upward by 3/4 in at midspan so it ends up closer to flat once the slab is poured. For the concrete trade this matters because a cambered beam under a slab on metal deck changes the slab thickness at midspan if the slab is finished level.

Shear studs

A number in brackets after a beam size, such as "(18)", is commonly the number of headed shear studs welded to the top flange, making the beam act compositely with the slab. Confirm the notation in the steel general notes.

T.O.S. elevations

T.O.S. is top of steel. Plans usually give one T.O.S. for the level with "U.N.O." (unless noted otherwise), and then call out exceptions next to individual members, such as "T.O.S. = 111'-8"" at a depressed area. Slab top elevations are then T.O.S. plus deck depth plus concrete above the deck, or whatever the slab section shows. How elevations and datums work is covered in grid lines and elevations on drawings.

Connection notes

On design drawings, connections are often shown only as typical details and design reactions, with the fabricator's engineer completing them on shop drawings. You may see end reactions written at beam ends, moment connection symbols at the beam end (the form varies; check the legend), and bracing drawn as diagonal lines in elevations. Materials are listed in the steel general notes, commonly ASTM A992 for W shapes, ASTM A500 for HSS, ASTM A36 for plates and angles, and ASTM F1554 for anchor rods. Read the notes on your set rather than assuming.

What concrete estimators need from the steel drawings

Even on a job where you only price concrete and rebar, the steel sheets hold items that are cast into, or sit on, your concrete:

Item on the steel drawings Why the concrete side needs it
Column base plates Set the top of pier or footing; grout space under the plate
Anchor rods Count, diameter, embedment, projection, templates
Embed plates with studs Cast into walls, beams and slab edges for steel connections
Beam pockets and bearing plates Openings and plates in concrete walls
Slab on metal deck Deck depth, slab thickness, edge angles, pour stops
T.O.S. elevations Slab top elevations and pour thickness
Steel columns at piers Pier sizes and rebar often sit on S-sheets of foundation plans

A common mistake is to treat the steel sheets as somebody else's problem and miss the embeds. Embed plates are usually supplied by the steel fabricator but placed by the concrete contractor, so they show up in the concrete scope as labor, layout and coordination. Your spec and contract decide who supplies what.

Worked example: steel columns on concrete piers

On the foundation plan, 12 steel columns sit on concrete piers on spread footings. The base plate detail shows:

  • Bottom of base plate at EL. 100'-0".
  • Grout 1-1/2" under the plate.
  • Pier 20" x 20".
  • Top of footing EL. 96'-0".
  • 4 anchor rods per column, 3/4" diameter.

Step 1, top of pier. Top of pier = bottom of plate minus grout = 100'-0" minus 1-1/2" = 99'-10 1/2".

Step 2, pier height. 99'-10 1/2" minus 96'-0" = 3'-10 1/2" = 3.875 ft.

Step 3, pier concrete. 20 in = 1.667 ft. Area = 1.667 x 1.667 = 2.778 ft². Volume per pier = 2.778 x 3.875 = 10.76 ft³. For 12 piers: 129.2 ft³ = 4.78 yd³ (about 3.66 m³).

Step 4, anchor rods. 12 x 4 = 48 rods, plus 12 setting templates. Take length, embedment and nut and washer requirements from the detail.

Step 5, check against steel. If the steel drawings say T.O.S. at the first framed level is 112'-0" and the column schedule says the column runs from base plate to that level, the column is 12'-0" long from bottom of plate. That is a cross-check that your pier top matches what the steel detailer assumes.

Run the volume through the concrete calculator. The pier rebar comes from the pier schedule or section, read the same way as any column schedule.

Where to start on a steel set

  1. Steel general notes: materials, connection design responsibility, camber and stud notation.
  2. Foundation plan: column locations, base plates, anchor rods, piers.
  3. Framing plans level by level: sizes, T.O.S., openings.
  4. Column schedule: column sizes by level and splice heights.
  5. Elevations and bracing: braced frames and their footings.
  6. Typical details: base plates, embeds, deck edges, beam bearing on concrete.

For the wider read order of the full set, see how to read structural drawings. To compare steel with concrete framing, the video concrete or steel structure is a good companion.

Frequently asked questions

What does W12x26 mean?

It is a wide flange steel shape with a nominal depth of 12 in and a weight of 26 lb per foot. The actual depth is about 12.2 in. The exact dimensions are in the AISC shape tables.

How do you read an HSS designation?

HSS6x6x1/4 is a square hollow section measuring 6 in by 6 in outside, with a nominal wall thickness of 1/4 in. Rectangular HSS give both outside dimensions, and round HSS give the outside diameter and wall thickness.

What does T.O.S. mean on steel drawings?

T.O.S. means top of steel, the elevation of the top flange of a beam. Plans usually give one T.O.S. for the level and note exceptions at individual members. It is used to set slab and deck elevations.

What does camber mean on a steel beam?

Camber is an upward curve built into the beam by the fabricator, noted as "c=3/4"" or similar. It offsets part of the deflection from the wet concrete and other loads, so the beam ends up closer to level.

Who places anchor bolts and embed plates?

It depends on the contract and specifications. A common arrangement is that the steel fabricator supplies them and the concrete contractor sets them in the forms before the pour. Always check the scope documents for your job.

This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.

Keep reading

The whole library

Free download

The Rebar Callout Cheat Sheet

One printable page: the five questions every callout answers, four labels decoded, and the same bar in six notations. Keep it next to the set of plans.

Plus a few short emails on reading structural drawings. Unsubscribe any time. Privacy.