Grid Lines and Elevations on Drawings: Finding Where and How Deep

Grid lines on drawings are the building's coordinate system: a set of lines, usually numbered one way and lettered the other, that every column, wall and footing is dimensioned from. Elevations are the third coordinate, the height of a surface such as top of footing (T.O.F.) or top of steel (T.O.S.), measured from a datum. With the grid you find where something is; with the elevation you find how high or how deep it is.
This guide explains how grid lines on drawings are labelled and dimensioned, how elevations and datums work, and then works out a footing depth from the numbers on a real-looking foundation plan.
Grid lines on drawings: what they are
A grid line is a long chain line (long dash, short dash) running across the plan, ending in a circle called a grid bubble. The bubble holds the grid name. The same grid appears on every plan, section and elevation of the building, on the architectural sheets as well as the structural ones, so "column at B-3" means the same point everywhere.
Grids are usually placed on column centers, or on a wall face or centerline. The structural notes or the first plan tell you which. If the grid runs along the face of a wall on one side of the building and the centerline of columns elsewhere, you must know that before you dimension anything.
Numbering and lettering conventions
| Convention | Typical practice |
|---|---|
| One direction | Numbers: 1, 2, 3 ... |
| Other direction | Letters: A, B, C ... |
| Letters skipped | I and O are often left out, so they are not confused with 1 and 0 |
| Added grids | 2.5 or B.1 for a grid between two main grids |
| Large buildings | Double letters (AA, BB) or prefixed grids per wing |
| Curved or angled wings | Separate grid system, often with its own prefix |
Which direction gets numbers and which gets letters varies between offices; there is no fixed rule. Read the bubbles, not your expectation.
Dimensions to grid
Structural plans dimension almost everything to grid lines, not to each other. A typical plan has:
- An overall string from the first grid to the last.
- A grid string with each bay, such as 24'-0" + 24'-0".
- Local dimensions from a grid to a wall face, slab edge, opening or footing edge.
When a footing is "centered on grid", its center sits on the intersection and you need only its size from the schedule. When it is offset, the plan shows a dimension from the grid to the footing edge or centerline. A common mistake is to measure a length grid to grid and forget that the slab edge or exterior footing extends past the grid by a dimension shown only once, at one corner.
Do not scale grid spacing from the sheet if a dimension is written. Scaling is a check, not a source; see how to scale a drawing.
Elevations: the third coordinate
Datum
Every elevation is measured from a datum. Two systems are common:
| System | How it looks | Where you see it |
|---|---|---|
| Project datum | First floor = EL. 100'-0" (or ±0.00) | Building sets, so most numbers are positive and easy to subtract |
| Survey datum | EL. 312.45 ft or +45.20 m above a benchmark | Civil sheets, site plans, some structural sets |
The general notes or the first plan usually state the relationship, such as "EL. 100'-0" = 312.45 ft survey datum". Never mix a number from the civil sheets with one from the structural sheets until you have converted them to the same datum.
The common elevation labels
| Label | Meaning |
|---|---|
| EL. | Elevation |
| F.F. / FFL | Finished floor (level) |
| T.O.S. | Top of slab or top of steel; check which in the abbreviations |
| T.O.F. | Top of footing |
| B.O.F. | Bottom of footing |
| T.O.W. | Top of wall |
| T.O.C. | Top of concrete (sometimes top of curb) |
| T.O.P. | Top of pier or top of pile cap, depending on the set |
T.O.S. is the classic trap: on a concrete set it usually means top of slab, on a steel set top of steel. The abbreviations guide has the full list.
How elevations appear on drawings
On plans you will see notes like "T.O.F. EL. 98'-8" U.N.O." or a spot elevation next to a footing. On sections, a level marker (a quartered circle or a triangle on a line) labels each important surface. The symbol is covered in structural drawing symbols.
Some sets give only the top elevation and the thickness, leaving you to find the bottom. Others give B.O.F. directly. Either way, you need both top and bottom to price excavation, concrete and bar lengths for dowels.
Worked example: footing depth from the elevations
The foundation plan above says: footings F1 typical, T.O.F. EL. 98'-8" U.N.O. The general notes say: first floor F.F. EL. 100'-0" = survey 312.45 ft. The footing schedule says F1 is 5'-0" x 5'-0" x 1'-4". The civil grading plan shows finished grade around the building at survey 311.95 ft.
Step 1, bottom of footing. B.O.F. = T.O.F. minus thickness = 98'-8" minus 1'-4" = 97'-4".
Step 2, convert the grade to the project datum. Grade is 312.45 minus 311.95 = 0.50 ft below the floor. 0.50 ft = 6 in. So grade is at EL. 99'-6".
Step 3, depth below grade. Grade 99'-6" minus B.O.F. 97'-4" = 2'-2" from finished grade to the bottom of the footing. If the general notes state a minimum footing depth below grade (for frost, for example), this is the number you compare against it.
Step 4, depth below the slab. Floor 100'-0" minus T.O.F. 98'-8" = 1'-4" from the top of slab to the top of footing. With a 4" slab, there is 1'-0" of fill or a pier between the slab underside and the footing top.
Step 5, quantities. - Concrete per footing: 5 x 5 x 1.333 = 33.3 ft³. Six footings: 200 ft³ = 7.41 yd³ (about 5.66 m³). - Footing excavation, for a rough check: B.O.F. to grade is 2'-2" (2.167 ft) per footing, before working space and side slopes, which depend on soil and the safety plan.
Step 6, the bay check. Grid string: 24'-0" + 24'-0" = 48'-0". The six footings sit on 3 x 2 = 6 grid intersections, which matches the count. Always check that the number of footings on the schedule matches the number of grid intersections that carry columns.
Check the volume with the concrete calculator. For the full read of a foundation sheet, see reading a foundation plan.
Metric sets
Metric sets work the same way, in metres to two or three decimals. A typical note reads "FFL ±0.00 = +45.20" (above a national datum). A footing might be marked T.O.F. -1.10 and 0.40 thick, so B.O.F. = -1.50. Negative numbers below the floor are normal; just subtract carefully.
Common mistakes
- Mixing datums. Taking grade from the civil sheet in survey feet and the footing from the structural sheet in project feet.
- Reading T.O.S. as the wrong thing. Slab on one set, steel on another.
- Ignoring "U.N.O.". One typical T.O.F. on the plan, with exceptions written next to individual footings at stepped areas.
- Grid face or center. Treating a grid on a wall face as if it were on the centerline adds or loses half the wall thickness on every dimension.
- Assuming numbering direction. Read the bubbles; letters and numbers can run either way.
Frequently asked questions
What are grid lines on drawings?
They are reference lines, usually through column centers, that form the building's coordinate system. They are numbered in one direction and lettered in the other, and they appear on every plan and section so all trades locate elements from the same lines.
Why are I and O skipped in grid lines?
They are often left out because they are easily confused with the numbers 1 and 0. Not every office follows this, so always read the actual bubbles on your set.
What does T.O.F. mean on a drawing?
T.O.F. means top of footing, the elevation of the footing's top surface. With the footing thickness from the schedule you can find the bottom of footing (B.O.F.), which sets excavation depth.
What is a datum on construction drawings?
A datum is the reference height that all elevations are measured from. Building sets often set the first floor at EL. 100'-0" or ±0.00, and the general notes relate that to a survey benchmark used on the civil sheets.
How do I find the depth of a footing below grade?
Find B.O.F. (T.O.F. minus thickness, or given directly), convert finished grade from the civil sheets to the same datum, and subtract. The result is the depth from grade to the footing bottom, which you compare to any minimum depth in the general notes.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.