How to Read a Column Schedule: Marks, Sizes, Bars, Ties and Splices

A column schedule is a table that gives, for each column mark and each level range, the column size, the vertical bars, the ties and their spacing. You read it by finding the column's mark on the plan, then reading down its column (or across its row) level by level, from the footing to the roof. Splice locations and lap lengths come from the schedule notes or a typical column detail.
A column schedule replaces dozens of elevation drawings with one grid. It is compact, and that is exactly why it is easy to misread. This article explains each part and then reads one column through three levels.
Where column marks come from
On the framing plans and foundation plan, each column carries a mark: C1, C2, C3 and so on. Columns with the same mark are built identically. Some offices mark columns by grid location instead (for example "B-2"), and the schedule then has one column per grid intersection.
Start by counting how many columns carry each mark. A column schedule usually does not give quantities.
The two common layouts
Vertical layout. The column marks run across the top, and the levels run down the side, top of the building at the top of the sheet. Each cell between two level lines describes that column over that storey. This layout is common in US practice because it looks like the building.
Horizontal layout. Each row is a column mark (or a mark plus level range), and the columns of the table are size, vertical bars, ties and remarks. This is common in smaller projects and in many other countries.
Both carry the same information. Read the headings and the level lines before you read any cell.
What each cell tells you
| Item | Typical entry | Meaning |
|---|---|---|
| Mark | C1 | Column type, repeated on the plans |
| Level range | L1 to L2 | The storey this entry applies to |
| Size | 16" × 16" | Cross-section of the column |
| Vertical bars | 4 #9 | Number and size of longitudinal bars |
| Ties | #3 @ 12" | Tie size and spacing over the height |
| Tie pattern | Type A | Refers to a typical tie arrangement sketch |
| Splice | Lap 5'-0" above L2 | Where and how bars join the bars above |
| Remarks | See detail 4/S-501 | Anything special |
Sizes per level
Column sizes often reduce as you go up, because the load reduces. When the size changes at a floor, the vertical bars from below cannot just continue straight. They are offset-bent into the smaller section, or stopped and replaced by dowels. The typical column detail shows which. For the estimator, an offset bend adds a little length and a size change usually means a new bar set.
Vertical bars
"4 #9" is four #9 bars, one in each corner of a square column. Larger counts (8, 12, 16) are spread around the perimeter. If bar sizes change from one level to the next, the schedule shows a new entry, and the splice is between the lower and the upper bars.
Ties and spacing
"#3 @ 12"" is #3 ties every 12 inches over the height of that storey. Some schedules show closer spacing near the top and bottom of the column (common in seismic design), written as two values or with a reference to a detail. A tie pattern reference (Type A, Type B, or a small sketch at the bottom of the schedule) shows how the ties wrap the bars: one perimeter tie for four bars, or extra cross ties or diamond ties for more bars. Each extra tie in the pattern is counted at every tie level. For the bars themselves, see stirrups and ties.
Splice location
Column bars are normally spliced just above a floor, where they are easy to place, by lapping the bars above with the bars below. The schedule or the typical detail tells you:
- Where: for example "splice above top of slab at each level".
- How long: a lap length per bar size, either in the schedule or in a lap table in the general notes.
- How: lap splice or mechanical coupler.
Lap lengths depend on the code, bar size, concrete strength and grade. Take them from the project's notes, not from a rule of thumb; see lap splice length.
Level ranges: reading top to bottom
The levels on the side of the schedule are usually labelled with names and elevations: Roof +26'-0", L2 +14'-0", L1 0'-0", top of footing -1'-6". Each storey's entry runs from one level line to the next. When an entry spans two or more storeys (the same size and bars from L1 to L3, for example), the schedule merges the cells. A common mistake is to read a merged cell as one storey and miss a level of bars.
Worked example: column C1 through three levels
This is an invented example. The plans show six columns marked C1. The schedule gives:
| Level range | Size | Vertical bars | Ties | Splice |
|---|---|---|---|---|
| L2 to Roof (+14'-0" to +26'-0") | 16" × 16" | 4 #8 | #3 @ 12" | hook into roof, per detail |
| L1 to L2 (0'-0" to +14'-0") | 16" × 16" | 4 #9 | #3 @ 12" | lap 5'-0" above L2 |
Further information from the notes and typical details (project values for this example):
- Column dowels from the footing are taken off with the footings.
- Upper bars stop 3 in below the top of the roof slab and turn a 1'-0" hook leg.
- Tie length per the typical tie detail: perimeter at 1.5 in cover plus 4 in for each of the two hooks.
Step 1: lower vertical bars (L1 to L2)
Length = storey height + lap above L2 = 14'-0" + 5'-0" = 19.0 ft.
Per column: 4 bars × 19.0 = 76.0 ft. For six columns: 456.0 ft.
Weight = 456.0 × 3.400 lb/ft = 1,550.4 lb of #9.
Step 2: upper vertical bars (L2 to roof)
Straight length = 26'-0" − 14'-0" − 0'-3" = 11'-9" = 11.75 ft. Add the hook leg: 11.75 + 1.0 = 12.75 ft.
Per column: 4 × 12.75 = 51.0 ft. For six columns: 306.0 ft.
Weight = 306.0 × 2.670 = 817.0 lb of #8.
Step 3: ties
Tie length: the tie sits at 1.5 in cover, so its outside dimensions are 16 − 3 = 13 in each way. Perimeter = 4 × 13 = 52 in. Add 2 × 4 in for hooks = 60 in = 5.0 ft.
Number of ties: L1 to L2 = 168 ÷ 12 + 1 = 15. L2 to roof = 144 ÷ 12 + 1 = 13. Total per column = 28.
Six columns: 168 ties × 5.0 ft = 840.0 ft × 0.376 = 315.8 lb of #3.
This simple count does not subtract the ties that are not placed inside a beam-column joint, and does not add closer spacing at the ends. On real drawings, read the tie notes for both before you finish. More on the method in how to estimate rebar for columns.
Summary
| Item | Bar | Total length (ft) | Weight (lb) |
|---|---|---|---|
| Lower verticals | #9 | 456.0 | 1,550.4 |
| Upper verticals | #8 | 306.0 | 817.0 |
| Ties | #3 | 840.0 | 315.8 |
| Total C1 (6 columns) | 2,683.2 |
Bar weights are the standard ASTM A615 values, listed in the rebar sizes reference.
Things the schedule does not say out loud
- Dowels. The bars that come up out of the footing are often in the footing schedule or a dowel detail, not the column schedule. Do not count them twice, and do not miss them.
- Joint ties. Whether ties continue through the depth of the beams at each floor is set in the typical details.
- Size changes. Offset bends or new dowels at a level where the size reduces.
- Top termination. How bars end at the roof: hooks, straight into a slab, or into a beam.
- Notes at the foot of the schedule. Tie patterns, lap tables and "UNO" defaults are often printed there in small text.
For how column reinforcement works structurally, see column reinforcement explained.
Frequently asked questions
What is a column schedule in structural drawings?
It is a table that lists each column type (mark) with its size, vertical reinforcement, ties and splice information for each level range. It replaces separate drawings for every column. The plans show where each mark is used.
Where are column bars spliced?
Most commonly just above each floor level, by lapping the upper bars with the lower bars. The schedule or typical column detail states the location and the lap length or coupler. Some designs splice at mid-height instead, so always read the detail.
What does #3 @ 12" mean in a column schedule?
It means #3 (10 mm) ties spaced 12 inches apart over the height of that column segment. Closer spacing near the ends, if required, is shown separately or in a typical detail.
Why do column sizes change between levels?
Lower columns carry the load of every floor above, so they are often larger or more heavily reinforced. As the load reduces up the building, the designer can reduce the size or the bars. The schedule shows each change at the level where it happens.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.