Rebar Takeoff for a House: A Full Worked Example

A rebar takeoff for a house is done element by element: perimeter footing, stem wall, interior grade beams, slab on grade, pad footings, columns and beams. For each one you count the bars, work out the cut lengths from the sections and details, add laps where runs exceed stock length, and convert length to weight. The totals are then summarised by bar size.
This article works through one complete small house. The house, its drawings and its numbers are an invented example made for teaching. Every value it uses (cover, laps, hooks) is stated as "from the drawings" for this example only. On a real job the project's general notes and governing code give these values.
The example house
The drawings show a single-storey house on a slab on grade:
- Rectangle 40'-0" × 28'-0", measured on the centreline of the perimeter footing.
- SF1 perimeter strip footing, 2'-0" wide × 1'-0" deep: 3 #5 continuous, #4 @ 12" transverse.
- Stem wall 8" thick × 2'-0" high on the footing: #4 @ 16" vertical dowels (3'-0" cut length), 2 #4 continuous horizontal.
- GB1 interior grade beam across the 28 ft width at mid-length, 12" × 18": 2 #5 top, 2 #5 bottom, #3 stirrups @ 12".
- Slab on grade 4" thick, #4 @ 18" EW, inside the stem walls (39'-4" × 27'-4"), 2" edge cover.
- F1 pad footings, 3'-0" × 3'-0" × 1'-0", 4 #5 EW, at 4 columns supporting a carport roof.
- C1 columns 12" × 12", 10'-0" high, 4 #5 vertical, #3 ties @ 12".
- B1 beam 12" × 18", 15'-0" clear span between two of the columns (the other pair carries a timber beam outside this package): 3 #6 bottom, 2 #5 top, #3 stirrups @ 8".
General notes for this example: cover to footings 3"; lap 2'-6" for #5 and 2'-0" for #4; stock length 40 ft. Cut lengths of stirrups, ties and beam bars come from the bending details on the drawings.
Step 1: perimeter strip footing SF1
Run on the centreline = 2 × (40 + 28) = 136 ft. The centreline is the right line for a closed loop; see rebar estimate for footings.
Longitudinal bars, 3 #5 continuous. Each 40 ft bar adds 40 − 2.5 = 37.5 ft of run after its lap. 136 ÷ 37.5 = 3.63, so 4 bars and 4 laps per line (a closed loop has as many laps as bars).
Length per line = 136 + 4 × 2.5 = 146 ft. Three lines = 438 ft of #5.
Corner bars. The typical detail shows corner bars matching the longitudinal bars, 2'-6" each leg: 4 corners × 3 bars × 5.0 ft = 60 ft of #5.
Transverse bars, #4 @ 12". Length = 24 − 3 − 3 = 18 in = 1.5 ft. Count on a closed loop = 136 ÷ 1 = 136 bars. Total = 204 ft of #4.
Step 2: stem wall
Dowels, #4 @ 16". Count = 136 × 12 ÷ 16 = 102 dowels × 3.0 ft = 306 ft of #4. In this house the dowels are also the wall's vertical bars, so they are counted once, here.
Horizontal bars, 2 #4 continuous. Each 40 ft bar adds 40 − 2 = 38 ft. 136 ÷ 38 = 3.58, so 4 bars and 4 laps per line. Length per line = 136 + 4 × 2 = 144 ft. Two lines = 288 ft of #4.
Step 3: interior grade beam GB1
The beam runs 28 ft between the footing centrelines. The detail shows its bars running into the perimeter footing with a hook at each end, giving a cut length of 30'-0" per bar.
Main bars: 4 bars (2 top, 2 bottom) × 30 ft = 120 ft of #5.
Stirrups #3 @ 12": stirrups stop at the footing, so count over the 26 ft between the inside faces of the footing (each 1 ft from the centreline): 26 × 12 ÷ 12 + 1 = 27 stirrups. Cut length from the bending detail: 4'-6". Total = 27 × 4.5 = 121.5 ft of #3. Beam bar layouts are covered in rebar estimate for beams.
Step 4: slab on grade
Slab inside the stem walls: 39'-4" × 27'-4" (472 in × 328 in), edge cover 2", #4 @ 18" EW.
Bars running the long way, counted across the short side: (328 − 4) ÷ 18 = 18.0, so 18 spaces + 1 = 19 bars. Length = 39.33 − 0.33 = 39.0 ft, which fits in one 40 ft stock bar, so no laps. Total = 19 × 39 = 741 ft.
Bars running the short way, counted across the long side: (472 − 4) ÷ 18 = 26.0, so 27 bars. Length = 27.33 − 0.33 = 27.0 ft. Total = 27 × 27 = 729 ft.
Slab total = 741 + 729 = 1,470 ft of #4. If the slab were longer than a stock bar, laps would be added the same way as in the footing. More on slab layouts in rebar estimate for a slab.
Step 5: pad footings F1
Bar length = 36 − 3 − 3 = 30 in = 2.5 ft. 4 bars EW = 8 bars per footing. Four footings = 32 bars × 2.5 = 80 ft of #5.
Column dowels: 4 #5 per column, 4'-0" cut length from the detail: 16 × 4.0 = 64 ft of #5.
Step 6: columns C1
Vertical bars: 4 #5 per column, cut length from the column schedule 11'-6" (including the lap with the dowels): 16 × 11.5 = 184 ft of #5.
Ties #3 @ 12": count = 10 × 12 ÷ 12 + 1 = 11 ties per column, 44 in all. Cut length from the detail: 3'-8" (44 in). Total = 44 × 44 ÷ 12 = 161.3 ft of #3. See rebar estimate for columns.
Step 7: beam B1
The beam detail gives bar cut lengths of 18'-0", including the anchorage into the columns.
- Bottom: 3 #6 × 18 = 54 ft of #6.
- Top: 2 #5 × 18 = 36 ft of #5.
- Stirrups #3 @ 8": 180 ÷ 8 = 22.5, round up to 23, + 1 = 24 stirrups × 4'-6" = 108 ft of #3.
Rebar takeoff for a house: summary by bar size
First the lengths by element:
| Element | #3 (ft) | #4 (ft) | #5 (ft) | #6 (ft) |
|---|---|---|---|---|
| SF1 strip footing | 204.0 | 498.0 | ||
| Stem wall | 594.0 | |||
| GB1 grade beam | 121.5 | 120.0 | ||
| Slab on grade | 1,470.0 | |||
| F1 footings + dowels | 144.0 | |||
| C1 columns | 161.3 | 184.0 | ||
| B1 beam | 108.0 | 36.0 | 54.0 | |
| Total length | 390.8 | 2,268.0 | 982.0 | 54.0 |
Then weights, using ASTM A615 unit weights from the rebar sizes reference:
| Size | Total length | lb/ft | Weight |
|---|---|---|---|
| #3 (10 mm) | 390.8 ft | 0.376 | 147.0 lb |
| #4 (13 mm) | 2,268.0 ft | 0.668 | 1,515.0 lb |
| #5 (16 mm) | 982.0 ft | 1.043 | 1,024.2 lb |
| #6 (19 mm) | 54.0 ft | 1.502 | 81.1 lb |
| Net total | 2,767.3 lb |
Check: 147.0 + 1,515.0 + 1,024.2 + 81.1 = 2,767.3 lb, about 1.38 US tons (1,255 kg). This is net. Waste goes on top as a separate, stated allowance; see rebar waste factor.
Notice where the weight is: the slab alone is over half the #4, and #4 is more than half the job. On a house, getting the slab right matters more than getting the column ties right.
What this example leaves out
A real rebar takeoff for a house often has items that this one does not. Look for them on every job:
- Thickened slab edges and interior thickenings under bearing walls, each with its own bars.
- Corner bars in the stem wall and bars at stem wall steps.
- Extra bars at re-entrant corners of the slab, from a typical detail.
- Hold-down or anchor bolts, usually not rebar but sometimes in the same package.
- Chairs and supports for the slab bars; see rebar chairs and accessories.
The same house is taken off for concrete in concrete takeoff for a house, which gives 34.86 yd³. That makes a useful check: the rebar here comes to about 79.4 lb per cubic yard of concrete for this design.
Frequently asked questions
How do you estimate rebar for a house foundation?
Take off each element separately: perimeter footing, stem wall, grade beams, slab, pad footings, columns and beams. Count bars from the spacings, take lengths from the dimensions minus cover plus hooks and laps, then multiply the total length of each size by its weight per foot.
How much rebar does a house need?
It depends on the size of the house, the foundation type, the soil and the engineer's design, so there is no standard figure. The invented example in this article needs about 2,767 lb net, but a real house can be much lighter or heavier. Take the number from a takeoff of the actual drawings.
What bar sizes are common in a house foundation?
4 and #5 are common for slabs, footings and stem walls in residential work, with #3 for stirrups and ties. The drawings and general notes set the sizes for each house.
Do dowels count as part of the footing or the wall?
Either is fine as long as you count them once. In this example the stem wall dowels are also its vertical bars, so they appear once under the stem wall.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.