Concrete Takeoff for a House: Footings, Slab and Columns Worked Through

A concrete takeoff for a house is length × width × depth for each element, done one element at a time: footings, stem walls, grade beams, slab, pads, columns and beams. You choose measuring lines that do not count the same concrete twice where elements meet, deduct blockouts and openings, and total the volume in cubic feet, then convert to cubic yards (÷ 27) or cubic metres (× 0.0283168).
This article takes off one small house from start to finish. The house and its numbers are an invented example for teaching. It is the same house used in rebar takeoff for a house, so the two articles can be read together.
The example house
From the drawings:
- Rectangle 40'-0" × 28'-0", measured on the centreline of the perimeter footing.
- SF1 perimeter strip footing, 2'-0" wide × 1'-0" deep.
- Stem wall 8" thick × 2'-0" high, centred on the footing.
- GB1 interior grade beam, 12" wide × 18" deep, across the 28 ft width.
- Slab on grade 4" thick, inside the stem walls, with one 4'-0" × 6'-0" blockout for a shower recess poured later.
- F1 pad footings 3'-0" × 3'-0" × 1'-0" under 4 carport columns.
- C1 columns 12" × 12", 10'-0" from top of footing to underside of beam.
- B1 beam 12" × 18", 15'-0" clear span between two of the columns.
Step 1: perimeter strip footing SF1
Centreline run = 2 × (40 + 28) = 136 ft.
Volume = 136 × 2.0 × 1.0 = 272.0 ft³.
For a closed rectangle, the centreline length times the section area gives the exact volume: at each corner the overlap on the inside balances the missing piece on the outside. Using the outside perimeter (2 × (42 + 30) = 144 ft) would overstate the footing by 16 ft³.
Step 2: stem wall
The stem wall sits on the same centreline. Volume = 136 × 0.667 × 2.0 = 181.3 ft³ (8 in = 0.667 ft).
Keep the footing and the stem wall as separate lines even though they are measured the same way. They are often poured separately, and the supplier and crew need the quantity per pour.
Step 3: interior grade beam GB1
GB1 runs between the perimeter footings. Measure it between the inside faces of the footing, not between centrelines, or its ends would be counted again inside the footing volume.
Length = 28 − 1 − 1 = 26 ft (the footing is 2 ft wide, so its inside face is 1 ft from the centreline).
Volume = 26 × 1.0 × 1.5 = 39.0 ft³.
Step 4: slab on grade
The slab is poured inside the stem walls. Each stem wall face is 4 in from the centreline, so the slab measures:
- 40 − 0.667 = 39.33 ft
- 28 − 0.667 = 27.33 ft
Area = 39.33 × 27.33 = 1,075.1 ft². Volume = 1,075.1 × 0.333 = 358.4 ft³.
GB1 sits under the slab with its top at the underside of the slab, so there is no overlap to deduct.
Deductions
The shower recess blockout: 4 × 6 × 0.333 = 8.0 ft³.
Net slab = 358.4 − 8.0 = 350.4 ft³.
Deduct openings and blockouts that are large enough to matter and are shown on the drawings. Small items like pipe sleeves, and the volume of the reinforcing steel, are not usually deducted. If the slab has thickened edges or interior thickenings under walls, add them as their own lines: a thickening is extra concrete below the 4 in slab, measured as its extra depth times width times length. More on slab layouts in slab on grade reinforcement.
Step 5: pad footings, columns and beam
F1 pads: 4 × 3.0 × 3.0 × 1.0 = 36.0 ft³.
C1 columns: measured from top of footing to underside of beam, so the column does not overlap the pad or the beam. 4 × 1.0 × 1.0 × 10.0 = 40.0 ft³.
B1 beam: clear span between the column faces. 1.0 × 1.5 × 15.0 = 22.5 ft³.
With these two rules, the block of concrete where the beam sits on top of each column (1.0 × 1.0 × 1.5 = 1.5 ft³) is part of neither line. Add it if you want the exact figure; here it is 3.0 ft³ for the two columns under B1 and is left out of the totals below, so the example stays simple. On a small job it barely moves the total; on a large frame decide one rule (columns to underside of beams, beams between column faces, joints added separately or counted with the beams) and use it everywhere.
Concrete takeoff for a house: summary in yd³ and m³
| Element | ft³ | yd³ | m³ |
|---|---|---|---|
| SF1 strip footing | 272.0 | 10.07 | 7.70 |
| Stem wall | 181.3 | 6.72 | 5.13 |
| GB1 grade beam | 39.0 | 1.44 | 1.10 |
| Slab on grade (net of blockout) | 350.4 | 12.98 | 9.92 |
| F1 pad footings | 36.0 | 1.33 | 1.02 |
| C1 columns | 40.0 | 1.48 | 1.13 |
| B1 beam | 22.5 | 0.83 | 0.64 |
| Total | 941.2 | 34.86 | 26.65 |
The totals are calculated from the unrounded cubic feet: 941.2 ÷ 27 = 34.86 yd³ and 941.2 × 0.0283168 = 26.65 m³. Adding the rounded rows gives a figure one hundredth lower, which is only rounding. This is a net quantity; any allowance for waste, spillage and over-excavation goes on top as a separate, stated line.
Conversion factors: 1 yd³ = 27 ft³; 1 ft³ = 0.0283168 m³; 1 yd³ = 0.7646 m³. You can check any of the lines with the concrete calculator.
Group the quantity by pour
The supplier orders by pour, not by element. A typical grouping for this house:
| Pour | Elements | yd³ |
|---|---|---|
| 1 | SF1 + F1 pads | 11.40 |
| 2 | Stem wall | 6.72 |
| 3 | GB1 + slab | 14.42 |
| 4 | C1 columns + B1 beam | 2.31 |
Pour 1 = (272.0 + 36.0) ÷ 27 = 11.41 yd³ from the unrounded sum; the table shows the sum of the rounded rows (10.07 + 1.33 = 11.40). Either is fine as long as the totals agree within rounding. The pour sequence on a real job comes from the contractor and the drawings' construction joint details; see construction joints and rebar.
Common mistakes in a concrete takeoff for a house
- Counting corners twice by measuring each side of the footing to its outside corners. Use the centreline for a closed loop.
- Running interior beams to the centreline of the perimeter footing, which counts their ends twice.
- Measuring the slab to the outside of the stem wall, which counts the top of the stem wall twice.
- Forgetting thickened edges and interior thickenings, which can be a large share of a slab's concrete.
- Mixing units. Keep every dimension in feet (8 in = 0.667 ft, 4 in = 0.333 ft) before multiplying.
- Hiding waste in the dimensions. Take off net, then add the allowance as one visible line.
The general method for every element type is in concrete volume estimate. For bagged concrete on small pours, see how many bags of concrete.
Using the concrete takeoff to check the rebar
The rebar takeoff of the same house comes to 2,767.3 lb net. Divided by 34.86 yd³ that is about 79.4 lb of rebar per cubic yard for this design. If the rebar or the concrete takeoff had a large error, this ratio would move far from what you see on your own similar jobs. The method is in how to check a rebar takeoff.
Frequently asked questions
How do you calculate concrete for a house foundation?
Take off each element as length × width × depth in feet: footings, stem walls, grade beams, slab, pads and columns. Measure closed footings on their centreline and interior elements between faces so nothing is counted twice, subtract blockouts, then divide the total cubic feet by 27 for cubic yards.
How much concrete does a house foundation need?
It depends on the house size, foundation type and design, so there is no standard number. The invented example here needs 34.86 yd³ (26.65 m³) net, but a real house must be taken off from its own drawings.
Do you deduct rebar volume from concrete?
Estimators do not usually deduct the volume of the reinforcing steel or small sleeves. Large blockouts, openings and recesses shown on the drawings are deducted.
How do you convert cubic feet to cubic yards and cubic metres?
Divide cubic feet by 27 for cubic yards. Multiply cubic feet by 0.0283168 for cubic metres, or multiply cubic yards by 0.7646.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.