How Much Concrete for Footings: Spread, Strip and Stepped Footings in Cubic Yards

7 min read · By a practising structural engineer · Updated November 2026

Footing rebar for a retaining wall extension at the Harvard Street Bridge
Photo: MassDOT, Public domain, via Wikimedia Commons

To work out how much concrete for footings, multiply length × width × depth of each footing in feet to get cubic feet, add them up, and divide by 27 to get cubic yards. Spread footings are counted from the plan and multiplied by their volume, strip footings are measured along their centreline, and stepped footings are split into simple blocks. A waste allowance, stated as a percentage, goes on top of the net volume.

That is all a concrete footing calculator does. Doing it by hand from the drawings once shows you where the calculator's inputs come from, and where people put the wrong ones in.

What you need from the drawings

Footing concrete comes from the same sheets as footing rebar:

  • Foundation plan: footing marks and locations, wall lines for strip footings, steps in footing level.
  • Footing schedule: size and depth for each spread footing mark, e.g. F1 4'-0" × 4'-0" × 1'-6".
  • Footing sections: width and depth of strip footings, keys, thickened areas.
  • Step details: how a strip footing steps down a slope, with the rise and the riser thickness.
  • General notes: concrete strength and sometimes a minimum footing depth below grade.

If the foundation system is new to you, foundation types on drawings explains what each mark usually is.

Before you work out how much concrete for footings is needed, get the units straight: 1 cubic yard = 27 cubic feet = 0.7646 m³. Convert inches to feet before you multiply (18 in = 1.5 ft). Mixing inches and feet in one product is a common arithmetic error in footing takeoffs.

Spread footings

A spread footing is a rectangular block, so:

Volume (ft³) = length × width × depth

Count each mark on the plan and multiply. A 4'-0" × 4'-0" × 1'-6" footing is 4 × 4 × 1.5 = 24 ft³ = 0.89 yd³.

Do not deduct the column dowels or the rebar. Their volume is too small to matter in an estimate.

Strip (continuous) footings and the centreline rule

A strip footing is a long rectangle in section, so its volume is section area × length. The question is which length.

Measure along the centreline of the footing. For a closed rectangle, the centreline run is exact: at each corner the outside half of the footing is short by one small square and the inside half is long by the same square, so they cancel.

  • Outside perimeter: overstates the volume.
  • Inside perimeter: understates it.
  • Centreline: correct for a closed loop.
SF1 2'-0" x 1'-0"perimeter stripoutside 52' x 32'centreline 50' x 30'inside 48' x 28'run = 2 x (50 + 30)= 160 ft
Strip footing SF1 in plan. The dashed centreline gives the correct run for a closed loop: 160 ft. The outside edge would give 168 ft and the inside edge 152 ft.

Interior strip footings that meet the perimeter footing in a T are different. Measure the interior run only to the face of the perimeter footing, otherwise the junction is counted twice.

Where a spread footing sits under a strip footing (a pad at a column in a wall line), deduct the overlap or measure the strip only up to the pad.

Quick reference: concrete per 100 ft of strip footing

Strip footing (width × depth) yd³ per 100 ft m³ per metre
16 in × 8 in 3.29 0.083
20 in × 10 in 5.14 0.129
24 in × 12 in 7.41 0.186
30 in × 12 in 9.26 0.232
36 in × 12 in 11.11 0.279
24 in × 18 in 11.11 0.279

These are pure geometry (width × depth × length ÷ 27), net of any waste. Use the table to check your own figures; the sizes on your drawings decide what you actually take off.

Stepped footings

"Stepped footing" is used for two different things, and both are handled by breaking the concrete into rectangular blocks.

A stepped spread footing has two tiers, a wide lower block and a smaller block on top. Add the two volumes.

A stepped strip footing follows a sloping site by dropping in steps. Measure the run in plan along the centreline as usual, then add the extra concrete at each step. The step detail shows the riser: a vertical piece of concrete the width of the footing, as high as the step, with a thickness given in the detail.

column above1'-0"1'-6"8'-0"upper 5'-0" x 5'-0" x 1'-0"lower 8'-0" x 8'-0" x 1'-6"= 25 + 96 = 121 ft3
Stepped spread footing F3 in section. Each tier is a simple block; the footing volume is the sum of the two.

Worked example: how much concrete for footings on one building

All sizes are this example's; the project drawings govern.

  • F1 spread footings: 4'-0" × 4'-0" × 1'-6", quantity 10.
  • F3 stepped spread footings: lower tier 8'-0" × 8'-0" × 1'-6", upper tier 5'-0" × 5'-0" × 1'-0", quantity 2.
  • SF1 perimeter strip footing: 2'-0" wide × 1'-0" deep, centreline 50'-0" × 30'-0".
  • SF1 steps down twice along one side. Step detail: riser 2'-0" high × 1'-0" thick, full footing width.
  • Waste allowance used here: 5%, as an example value only.

Step 1: F1

4 × 4 × 1.5 = 24 ft³ each. 10 × 24 = 240 ft³.

Step 2: F3

Lower tier 8 × 8 × 1.5 = 96 ft³. Upper tier 5 × 5 × 1.0 = 25 ft³. One footing = 121 ft³. Two = 242 ft³.

Step 3: SF1

Centreline run = 2 × (50 + 30) = 160 ft. Section = 2 × 1 = 2 ft². Volume = 160 × 2 = 320 ft³.

Step 4: steps

Each riser = 2 ft wide × 2 ft high × 1 ft thick = 4 ft³. Two steps = 8 ft³.

Step 5: total

Item Quantity Volume each (ft³) Total (ft³) Total (yd³)
F1 spread footings 10 24 240 8.89
F3 stepped spread footings 2 121 242 8.96
SF1 strip footing, 160 ft 1 320 320 11.85
SF1 step risers 2 4 8 0.30
Net total 810 30.00

810 ÷ 27 = 30.00 yd³ net (22.94 m³).

With the example's 5% allowance: 30.00 × 1.05 = 31.50 yd³.

Two things about that last number. First, the allowance is a company decision; state it on its own line so anyone checking the estimate can see the net figure. Second, an order is placed in the increments your supplier delivers, which is a purchasing step, not part of the takeoff.

You can check any single footing with the site's concrete calculator.

Where footing concrete estimates go wrong

  • Outside perimeter for strip footings. On the example it adds 8 ft of run, 16 ft³.
  • Inches multiplied as feet. A 1'-6" depth entered as 18 multiplies the volume by twelve. Convert first.
  • T-junctions counted twice. Interior strips stop at the face of the perimeter footing.
  • Earth-formed footings. When footings are poured straight into a trench, the trench is rarely the exact width on the drawing. The drawings give neat dimensions; any allowance for an oversized trench is a judgement you state, not a hidden fudge.
  • Pedestals, piers and keys. Short pedestals on top of footings and keys underneath are separate blocks. They are easy to miss because they sit in the column schedule or the section, not the footing schedule.
  • Steps. Each step adds a riser block. Count them on the foundation plan or the wall elevation.

The same dimensions feed the footing rebar, so it is efficient to do both in one pass; see rebar estimate for footings. For the rest of the concrete on a house, see concrete takeoff for a house, and for small pours by the bag, how many bags of concrete.

Frequently asked questions

How do you calculate concrete for a footing?

Multiply the length, width and depth in feet to get cubic feet, then divide by 27 for cubic yards. For a strip footing, use the centreline length times the section area. Add all footings together, then add any waste allowance as a separate stated percentage.

How many yards of concrete do I need for a 2 ft by 1 ft footing?

A strip footing 2 ft wide and 1 ft deep holds 2 ft³ per foot of length, so 100 ft of it needs 200 ft³, which is 7.41 yd³ before any waste. Multiply by your actual centreline length.

Should I measure strip footings on the outside or the centreline?

On the centreline. For a closed rectangular loop the centreline length gives the exact volume, while the outside perimeter overstates it and the inside perimeter understates it. Interior footings that join the perimeter are measured to the face of the perimeter footing.

How much extra concrete should I order for footings?

There is no single correct figure. It depends on how the footings are formed or dug, the site and the company's practice, so the allowance should be a stated percentage on its own line above the net volume. The example here uses 5% only to show the arithmetic.

This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.

Keep reading

The whole library

Free download

The Rebar Callout Cheat Sheet

One printable page: the five questions every callout answers, four labels decoded, and the same bar in six notations. Keep it next to the set of plans.

Plus a few short emails on reading structural drawings. Unsubscribe any time. Privacy.