Installation and reinforcement of a new CMU block wall
Photo: MTA Capital Construction Mega Projects, CC BY 2.0, via Wikimedia Commons

Rebar in CMU block walls runs in two directions. Vertical bars sit inside the hollow cells of the blocks, and only the cells with bars (plus any others the drawings call for) are filled with grout. Horizontal steel goes either in bond beams, which are courses of special U-shaped blocks filled with grout and bars, or as prefabricated wire joint reinforcement laid in the mortar beds. At the base, dowels from the footing lap with the vertical bars.

Counting rebar in CMU block walls is mostly a matter of turning bar spacing into cell positions and course heights into joints and bond beams.

Block geometry you need for the count

The standard US concrete masonry unit (CMU) is called 8x8x16. Those are nominal sizes; the actual block is 3/8 in smaller (7 5/8 x 7 5/8 x 15 5/8 in) so that with a 3/8 in mortar joint the module works out to 8 in high and 16 in long. A standard two-core stretcher has two cells, so along the wall there is a cell roughly every 8 in.

That 8 in module drives everything:

  • Vertical bar spacings are multiples of 8 in: 16, 24, 32, 40, 48 in.
  • Course heights are 8 in, so wall heights and bond beam levels are multiples of 8 in.
  • Joint reinforcement at 16 in on center means every other bed joint.

Other widths (6, 10, 12 in) follow the same 8 x 16 face module. Metric blocks in other countries use different modules (often 200 x 400 mm faces), so read the block size on the drawings.

Why the steel is where it is

A block wall carries vertical load well in compression, but it is weak in tension, the same as concrete. Wind or soil pressure bends the wall out of plane, putting one face in tension. A retaining or basement wall bends one way only, so its vertical bars are often placed toward the tension face, and the wall section shows the bar position in the cell. Many walls have bars centered in the cell instead, since the wind can come from either side.

Horizontal steel ties the wall together along its length, controls shrinkage cracking, and in bond beams works as a beam over openings or at the top of the wall where the roof or floor bears. If the wall spans horizontally between pilasters, the horizontal steel becomes the main steel.

BOND BEAMJOINT REINF@ 16" O.C.DOWELVERT @ SPACING
Reinforced CMU wall elevation. Shaded cells are grouted. Vertical bars (red) sit in grouted cells and lap with hooked dowels from the footing; a bond beam with horizontal bars caps the wall; ladder joint reinforcement (blue, dashed) sits in every other bed joint.

The four kinds of rebar in CMU block walls

Steel Where it goes How it shows on drawings Takeoff unit
Vertical bars In cells, grouted solid #5 @ 32" O.C. VERT, plus bars each side of openings and at corners and wall ends Count from spacing x length
Bond beam bars In bond beam courses (channel or knock-out blocks) BOND BEAM W/ 2-#5 CONT. at a level or "at top of wall", "at floor level" Linear feet x bars, plus laps
Joint reinforcement Mortar bed joints 9 GA. LADDER JOINT REINF. @ 16" O.C. Linear feet per joint line
Dowels From footing or slab into the wall #5 DOWEL TO MATCH VERT. with embedment and lap Count = number of vertical bars

Vertical bars and grouted cells

The structural plan or wall schedule gives the spacing. On top of the regular spacing, the typical masonry detail usually requires bars at wall ends, at corners, at intersections and at each side of openings. Those extra bars often make the difference between a good and a poor count. Read the masonry general notes and the typical details before you start.

Only cells with bars are grouted in a partially grouted wall. The estimator for the masonry trade counts grouted cells for grout volume; the rebar estimator counts bars. Both start from the same cell positions.

Bond beams

A bond beam is a horizontal course built with U-shaped or knock-out web blocks so bars can lie in a continuous channel, then filled with grout. Look for them at the top of walls, at floor and roof bearing levels, and over openings where they double as lintels (see lintel reinforcement). The bars run continuously, so add laps where the wall is longer than your stock length; lap splice length explains how laps are counted.

Joint reinforcement

Prefabricated wire, two longitudinal wires with cross wires, laid in the mortar joints. The ladder type has cross wires at right angles; the truss type has diagonal cross wires. NCMA guidance (TEK 12-2B) says truss-type should not be used in reinforced or grouted walls, because the diagonals get in the way of vertical bars and grout. It is usually taken off in linear feet and is often supplied by the mason rather than the rebar subcontractor. Check the scope split.

Dowels from the footing

Each vertical bar needs a dowel from the foundation, set in the footing before the wall is built, with a lap above the footing. The foundation plan or wall section gives the dowel size, embedment, hook and lap. It is easy to forget them because they are shown on the foundation sheet, not the wall elevation; see reading a foundation plan.

Worked example: a 40 ft partially grouted wall

A straight 8 in CMU wall, 40 ft (12.19 m) long, 10'-8" (3.25 m) high = 16 courses. No openings. Notes:

  • Vertical: #5 @ 32" O.C., including one bar in each end cell. Vertical bar length 10'-6".
  • Dowels: #5 to match vertical, total length 3'-6" including hook and lap.
  • Bond beam at top of wall: 2-#5 CONT.
  • Joint reinforcement: 9 GA. LADDER @ 16" O.C. in the courses below the bond beam.

Step 1: Cell positions. 40 ft = 480 in. The first and last cell centers are about 4 in from each end, so the distance between end cells is 480 - 8 = 472 in.

Step 2: Vertical bars. 472 / 32 = 14.75, round up to 15 spaces, 16 bars. (Rounding up means the last space is slightly shorter. The spacing on the drawing is a maximum.) The wall has 480 / 8 = 60 cells; 16 of them are grouted.

Step 3: Vertical bar weight. 16 x 10.5 ft = 168 ft x 1.043 lb/ft = 175.2 lb.

Step 4: Dowels. 16 x 3.5 ft = 56 ft x 1.043 = 58.4 lb.

Step 5: Bond beam. 2 bars x 40 ft = 80 ft x 1.043 = 83.4 lb. Taken from 40 ft stock, no lap; with 20 ft stock you would add one lap per bar.

Step 6: Joint reinforcement. Bed joints at 16, 32, 48, 64, 80, 96 and 112 in above the base = 7 joint lines (the next level, 128 in, is the top of the wall, in the bond beam course). 7 x 40 ft = 280 linear feet.

Item Quantity Weight
#5 vertical, 16 bars x 10'-6" 168 ft 175.2 lb
#5 dowels, 16 x 3'-6" 56 ft 58.4 lb
#5 bond beam, 2 x 40'-0" 80 ft 83.4 lb
Rebar total 317.1 lb (143.8 kg)
9 ga. ladder joint reinforcement 280 lf by the lf
Grouted cells 16 of 60 for the masonry estimate

With openings, add the bars each side of every opening and the lintel or bond beam over it, and leave out any regular-spacing bar that would fall inside the opening.

Common mistakes when counting rebar in CMU block walls

  • Using actual block dimensions for the module. Count with nominal 8 in and 16 in; the mortar joint makes up the difference.
  • Forgetting end, corner and opening bars. They are in the typical details, not the spacing callout.
  • Missing dowels. They live on the foundation drawings.
  • Taking joint reinforcement as rebar weight. It is wire, bought by length, and often the mason's scope.
  • Grouting every cell in the count. Partially grouted walls only grout the reinforced cells and bond beams, unless the notes say "grout solid".

Frequently asked questions

How far apart is rebar in a block wall?

The structural drawings set the spacing, and in standard CMU it is a multiple of 8 in because of the block module, for example 16, 24, 32 or 48 in on center. Extra bars are usually required at corners, wall ends and each side of openings.

Do all cells in a CMU wall need to be grouted?

No. In a partially grouted wall only the cells with vertical bars, and the bond beams, are grouted. Some walls are specified "grout solid", where every cell is filled. The general notes or wall schedule say which.

What is a bond beam in a block wall?

A bond beam is a horizontal course of U-shaped or knock-out blocks with horizontal bars laid in the channel and grouted. It ties the wall together and is placed at the top of walls, at floor or roof bearing levels and over openings.

What is the difference between joint reinforcement and rebar in a CMU wall?

Joint reinforcement is light prefabricated wire laid in the mortar bed joints, mainly to control cracking. Rebar is deformed bar placed in grouted cells and bond beams and carries the structural load. They are counted separately.

How do you calculate the number of vertical bars in a block wall?

Divide the distance between the end cells by the bar spacing, round up, and add one. Then add the extra bars the typical details require at corners, intersections and openings.

This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.

Keep reading

The whole library

Free download

The Rebar Callout Cheat Sheet

One printable page: the five questions every callout answers, four labels decoded, and the same bar in six notations. Keep it next to the set of plans.

Plus a few short emails on reading structural drawings. Unsubscribe any time. Privacy.