To work out how much rebar you need for a slab, count the bars in each direction (slab width minus edge distance, divided by the spacing, rounded up, plus one), multiply by the bar length including laps, and add the two directions together. For a 20 ft x 20 ft slab with #4 bars at 12 in each way, that comes to about 819 ft of bar (about 547 lb) before waste. The table below gives the same answer for other common slab sizes at 12 in and 18 in spacing.
The method matters more than the table, because your slab will not be exactly square, and the drawing (or the local code and your engineer) decides the bar size and spacing. The numbers here show how the count works; they are not a design.
What you need before you count
Four pieces of information decide how much rebar a slab takes:
- Slab length and width, outside dimensions.
- Bar size and spacing, written on the drawing as something like
#4 @ 12" O.C. E.W.(#4 bars, 12 in on center, each way). If you need help reading that line, see how to read rebar callouts. - Edge distance, how far the outside bars sit in from the slab edge. This comes from the cover requirement on the drawing.
- Stock length and lap length, because a run longer than one bar needs two bars overlapped.
If the slab is for a house, garage or shed, the bar size and spacing come from your plans or your local building department. Many small slabs on grade are built with welded wire, fibers, or no reinforcement at all, depending on the design. Do not pick a bar layout from a table on a website, including this one.
The method, step by step
Step 1: count the bars in one direction
Bars running east-west are spaced across the north-south dimension. Take that dimension in inches, subtract the edge distance at both sides, divide by the spacing and round up. That gives the number of spaces. Add one to get the number of bars.
Bars = roundup((width - 2 x edge) / spacing) + 1
Rounding up keeps the actual spacing at or below what the drawing asks for. Rounding down is the most common counting mistake.
Step 2: work out the length of each run
Each bar run is the slab length minus the edge distance at both ends. If that run is longer than your stock bar, you need laps. With 20 ft bars and a 2 ft lap, the first bar covers 20 ft and every extra bar adds 18 ft.
Step 3: repeat for the other direction, then add
For a rectangular slab the two directions have different counts and lengths, so calculate them separately. For a square slab they are the same, so double one direction.
Step 4: convert to weight
Multiply the total length by the weight per foot. For #4 bar (13 mm), ASTM A615 gives 0.668 lb/ft (0.994 kg/m). The rebar weight calculator and the rebar sizes reference have the other sizes.
Rebar for common slab sizes (table)
Assumptions for every row, so you can check the numbers yourself:
- Square slab, one mat, bars each way, #4 bars (0.668 lb/ft).
- 3 in edge distance on every side.
- 20 ft stock bars.
- 2 ft lap where a run needs two bars. This lap is an example assumption only; the real lap length comes from your project's general notes and the governing code (see lap splice length).
- No waste, no chairs, no edge or corner bars.
"Bars each way" is the number of bar runs in one direction. "20 ft bars, simple cut" is how many stock bars you need if each run is cut straight from stock and offcuts are not reused.
| Slab size | Spacing | Bars each way | Run length | Total length | Weight | 20 ft bars, simple cut |
|---|---|---|---|---|---|---|
| 10 x 10 ft | 12 in | 11 | 9.5 ft | 209 ft | 140 lb (63 kg) | 11 |
| 10 x 10 ft | 18 in | 8 | 9.5 ft | 152 ft | 102 lb (46 kg) | 8 |
| 12 x 12 ft | 12 in | 13 | 11.5 ft | 299 ft | 200 lb (91 kg) | 26 |
| 12 x 12 ft | 18 in | 9 | 11.5 ft | 207 ft | 138 lb (63 kg) | 18 |
| 20 x 20 ft | 12 in | 21 | 19.5 ft | 819 ft | 547 lb (248 kg) | 42 |
| 20 x 20 ft | 18 in | 14 | 19.5 ft | 546 ft | 365 lb (165 kg) | 28 |
| 24 x 24 ft | 12 in | 25 | 25.5 ft (1 lap) | 1,275 ft | 852 lb (386 kg) | 67 |
| 24 x 24 ft | 18 in | 17 | 25.5 ft (1 lap) | 867 ft | 579 lb (263 kg) | 46 |
| 30 x 30 ft | 12 in | 31 | 31.5 ft (1 lap) | 1,953 ft | 1,305 lb (592 kg) | 124 |
| 30 x 30 ft | 18 in | 21 | 31.5 ft (1 lap) | 1,323 ft | 884 lb (401 kg) | 84 |
Notes on the last column:
- 10 x 10: two 9.5 ft pieces come out of one 20 ft bar, so the bar count is half the number of pieces.
- 12 x 12: each 11.5 ft piece leaves an 8.5 ft offcut, which is why the stock count is high compared to the total length. A cutting plan that reuses offcuts, or 40 ft stock, changes this.
- 24 x 24: each run is one 20 ft bar plus a 5.5 ft piece lapped 2 ft. Three 5.5 ft pieces come out of one 20 ft bar.
- 30 x 30: each run is one 20 ft bar plus an 11.5 ft piece lapped 2 ft.
The gap between "total length" and "20 ft bars, simple cut" is cutting waste. That is why estimators add a waste allowance; see rebar waste factor.
Worked example: a 20 x 24 ft slab, #4 @ 18 in each way
Rectangular slabs are where people go wrong, so here is one worked in full with the same assumptions (3 in edge distance, 20 ft bars, 2 ft example lap).
Bars running the 24 ft direction are spaced across the 20 ft width. Available width = 20 x 12 - 2 x 3 = 234 in. Spaces = 234 / 18 = 13.0, so 13 spaces and 14 bars. Run length = 24 - 0.5 = 23.5 ft. That is more than 20 ft, so each run is a 20 ft bar plus a piece lapped 2 ft: length with lap = 23.5 + 2 = 25.5 ft. Total = 14 x 25.5 = 357 ft.
Bars running the 20 ft direction are spaced along the 24 ft length. Available length = 24 x 12 - 6 = 282 in. Spaces = 282 / 18 = 15.67, round up to 16, so 17 bars. Run length = 20 - 0.5 = 19.5 ft, which fits in one 20 ft bar with no lap. Total = 17 x 19.5 = 331.5 ft.
Total length = 357 + 331.5 = 688.5 ft. Weight = 688.5 x 0.668 = 460 lb (about 209 kg).
Stock bars, simple cut: the 24 ft direction needs 14 full bars plus 14 pieces of 5.5 ft (three per bar, so 5 bars), the 20 ft direction needs 17 full bars. That is 14 + 5 + 17 = 36 bars of 20 ft.
Then add what the table leaves out: chairs to hold the mat at the right height (see rebar chairs and accessories), any bars in thickened edges, dowels into existing concrete, and waste.
Things that change the count
Thickened edges and footings
Many slabs on grade turn down at the edges, and those turn-downs often carry their own continuous bars. They are counted along the perimeter, separately from the mat. The slab on grade reinforcement article covers how they appear in sections.
Two mats instead of one
Suspended slabs and some heavy slabs have top and bottom bars. Each mat is counted separately, and top bars are often only over the supports. A broader method for all slab types is in estimating rebar for a slab.
Openings and steps
Openings remove bars but usually add trim bars around them. Steps in the slab break bar runs. Read the details before you finalize the count.
Lap length
The 2 ft lap here is an example. Real lap lengths depend on bar size, concrete strength, bar position and the code in force, and the general notes on the drawing override anything you read online.
Frequently asked questions
How much rebar do I need for a 20x20 slab?
With #4 bars at 12 in each way, one mat and a 3 in edge distance, a 20 x 20 ft slab takes 21 bars each way, 819 ft in total, about 547 lb before waste. At 18 in spacing it is 14 bars each way and 546 ft. Your drawings or local building department decide the actual bar size and spacing.
How do I calculate rebar spacing for a slab?
You do not calculate it as the builder or estimator; the spacing is given on the structural drawings or by the code requirements that apply to your project. Once you have the spacing, the count is the width minus edge distances, divided by the spacing, rounded up, plus one.
Does every concrete slab need rebar?
No. Many slabs on grade use welded wire, fibers, or no reinforcement with closely spaced control joints. What a particular slab needs depends on its use, the soil and the local code, so check your plans or ask a local engineer or building official.
How many 20 ft bars do I need?
Divide each bar run into pieces you can cut from 20 ft stock, then count the stock bars. Dividing the total length by 20 gives the theoretical minimum, but offcuts mean you usually need more, as the table above shows.
Should I add extra rebar for waste?
Yes, estimators add a waste allowance for offcuts, damaged bars and miscounts. The right allowance depends on the job and how well the cutting is planned, so it is a company or project decision rather than a fixed number.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.