Elevator Pit Rebar Estimate: Slab, Walls, Corners, Sump and Dowels

An elevator pit rebar estimate is a small box taken off in five parts: the pit slab (top and bottom mats, both ways), the pit walls (vertical and horizontal bars at each face), the corner bars where the walls meet, the extra bars around the sump, and the dowels that connect the walls to the slab. It is a small quantity, but it has many bar types in a small space, which is why it is easy to miss a face or a set of dowels.
The pit is usually shown on the foundation plan as a recessed box with its own sections. Its walls often continue upward as the elevator core walls, so knowing where the pit stops and the core starts is the first decision.
Where to find pit reinforcement on the drawings
| Item | Usually found on | Typical callout |
|---|---|---|
| Pit slab top and bottom | Pit section or enlarged pit plan | #5 @ 12" EW T&B |
| Wall vertical bars | Pit section | #5 @ 12" VERT EF |
| Wall horizontal bars | Pit section | #4 @ 12" HORIZ EF |
| Corner bars | Typical wall corner detail | match horizontals, 2'-0" legs |
| Dowels slab to wall | Pit section | #5 dowels to match verticals |
| Sump | Sump detail | 2 #5 trim bars each side |
| Step from main slab or mat | Step detail | bars bent down into the pit |
The pit size and depth are set by the elevator supplier's requirements and shown by the architect and engineer; the estimator takes them from the drawings. If the pit sits inside a mat foundation, read this together with rebar estimate for a mat foundation, because the mat bars usually bend down into the pit or stop at it.
How to take off elevator pit rebar
Take it off in this order:
- Pit slab, bottom mat then top mat, both ways. Check whether the bottom bars hook up into the walls.
- Dowels from the slab into the walls, each face.
- Wall verticals, each face, from top of slab to the top of the pit wall, with any hook into the slab above.
- Wall horizontals, each face, row by row up the height.
- Corner bars from the typical corner detail.
- Sump trim bars and its own small cage.
A useful habit: list the faces before you count. A four-wall pit has eight wall faces (four inside, four outside), and every vertical and horizontal callout with EF applies to all eight.
For the faces, measure the inside face on the inside perimeter and the outside face on the outside perimeter. The outside face is always longer, and using the centreline for both faces understates one and overstates the other. The general method for walls is in rebar estimate for walls.
Worked example: a single elevator pit
The drawings for this invented example give:
- Pit inside 8'-0" × 7'-0", walls 12" thick, so the outside is 10'-0" × 9'-0".
- Pit slab 18" thick, #5 @ 12" EW top and bottom, 3" cover. Bottom bars hooked up 1'-0" at each end; top bars straight.
- Walls 5'-0" high above the pit slab, #5 @ 12" vertical EF with a 1'-0" hook into the floor slab above (cut length 6'-0"), #4 @ 12" horizontal EF, 6 rows per face.
- Dowels #5 to match the verticals, L-shaped: 1'-0" foot on the bottom mat, vertical leg 3'-8" (1'-2" inside the slab plus a 2'-6" lap from this example's lap schedule). Cut length 4'-8".
- Corner bars #4, 2'-0" × 2'-0", at every horizontal bar, each face, each corner.
- Sump 2'-0" × 2'-0" recess in the pit slab: 2 #5 × 4'-0" trim bars each side; 4 #4 U-bars × 6'-0" around the recess.
Step 1: pit slab
Bars running the 10 ft way, counted across 9 ft: (108 − 6) ÷ 12 = 8.5, round up to 9, + 1 = 10 bars. Straight length = 10 − 0.5 = 9.5 ft.
Bars running the 9 ft way, counted across 10 ft: (120 − 6) ÷ 12 = 9.5, round up to 10, + 1 = 11 bars. Straight length = 9 − 0.5 = 8.5 ft.
- Bottom mat, with 1'-0" hooks at both ends: 10 × 11.5 + 11 × 10.5 = 115.0 + 115.5 = 230.5 ft of #5.
- Top mat, straight: 10 × 9.5 + 11 × 8.5 = 95.0 + 93.5 = 188.5 ft of #5.
The sump interrupts a couple of top bars. Small interruptions are usually not deducted; the trim bars in step 5 replace the cut bars.
Step 2: dowels
Faces: inside perimeter = 2 × (8 + 7) = 30 ft; outside perimeter = 2 × (10 + 9) = 38 ft.
The walls form a closed loop, so the count on each face is perimeter ÷ spacing with no + 1: 30 + 38 = 68 dowels.
Length = 68 × 4.667 = 317.3 ft of #5.
Step 3: wall verticals
68 verticals (same count as the dowels) × 6.0 ft = 408.0 ft of #5.
Step 4: wall horizontals
Measured on each face's perimeter, 6 rows per face:
- Inside face: 30 × 6 = 180 ft.
- Outside face: 38 × 6 = 228 ft.
- Total = 408 ft of #4.
Measuring on the face perimeter is an estimating simplification: the real bars stop short of the corner by the cover and are joined by the corner bars. The difference is a few inches per bar.
Step 5: corner bars and sump
- Corner bars: 4 corners × 2 faces × 6 rows × (2 + 2 ft) = 192 ft of #4.
- Sump trim bars: 4 sides × 2 bars × 4 ft = 32 ft of #5.
- Sump U-bars: 4 × 6 ft = 24 ft of #4.
Summary
| Item | Size | Length |
|---|---|---|
| Pit slab bottom mat | #5 | 230.5 ft |
| Pit slab top mat | #5 | 188.5 ft |
| Dowels | #5 | 317.3 ft |
| Wall verticals | #5 | 408.0 ft |
| Sump trim bars | #5 | 32.0 ft |
| Wall horizontals | #4 | 408.0 ft |
| Corner bars | #4 | 192.0 ft |
| Sump U-bars | #4 | 24.0 ft |
| Size | Total length | lb/ft | Weight |
|---|---|---|---|
| #4 (13 mm) | 624.0 ft | 0.668 | 416.8 lb |
| #5 (16 mm) | 1,176.3 ft | 1.043 | 1,226.9 lb |
| Net total | 1,643.7 lb |
Check: 416.8 + 1,226.9 = 1,643.7 lb (745.6 kg). The pit holds 10 × 9 × 1.5 = 135 ft³ of slab and 34 ft (wall centreline) × 1 × 5 = 170 ft³ of walls, 305 ft³ = 11.30 yd³ in all, so this design is about 146 lb of rebar per cubic yard. Weights can be checked with the rebar weight calculator.
Notice that in this elevator pit rebar estimate the dowels alone are about a quarter of the #5. Leaving them out is a common pit error, and it happens because they appear only in the section, not on the plan.
Things to watch on elevator pits
- Where the pit ends and the core begins. If the pit walls continue up as the elevator core, the verticals may run through without a hook. Decide which line the bars above the pit belong to and count them once. Cores are covered in shear walls and cores.
- Pit inside a mat. The mat's bottom bars may run under the pit at a lower level, and the step detail adds bent bars. The pit slab may then be part of the mat reinforcement.
- Extra bars at the step. Where the main slab or mat steps down into the pit, the step detail often adds bars around the opening in the slab above.
- Waterproofing and joints. Pits are below the surrounding slab and can be below groundwater, so the drawings may show waterstops or a different cover. Read the pit section's notes; cover follows the project's notes, see concrete cover.
- Two pits side by side. A double elevator has a shared middle wall with its own faces and dowels.
Frequently asked questions
How do you estimate rebar for an elevator pit?
Take off the pit slab (top and bottom, both ways), then the wall verticals and horizontals at each face, the corner bars, the dowels from slab to walls, and the sump bars. Measure inside faces on the inside perimeter and outside faces on the outside perimeter, and use closed-loop counting with no + 1.
Why do elevator pit walls have bars on each face?
The walls hold back soil and often water from outside, and they connect to the slab and the core above, so the engineer usually places bars at both faces. The section shows the bars for each face; take each face as its own line.
Are elevator pit dowels counted with the slab or the walls?
Either, as long as they are counted once. Many estimators include them with the walls, since they lap with the wall verticals. Note your choice in the takeoff.
What is the sump in an elevator pit?
A small recess in the pit slab where water can collect and be removed. On the drawings it has its own detail, usually with trim bars around the recess and a few bars that wrap its sides.
This article explains general practice for learning purposes. On a real project, the drawings, the general notes and the governing code always win.